Last update at: 2025-12-18T04:30:00+00:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
| Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| < 51 52 53 54 55 > | ||||||||||||||||||
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_016 | Dismissed | Planned | Production unavailability | 2024-12-15T01:49:25+00:00 | 2024-08-27T08:00:00+00:00 | 2024-12-15T18:00:00+00:00 | MW | 165 | 0 | 165 | Failure | Plant Fault - Electrical Equipment |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_015 | Dismissed | Planned | Production unavailability | 2024-12-14T15:39:15+00:00 | 2024-08-27T08:00:00+00:00 | 2024-12-15T06:00:00+00:00 | MW | 165 | 0 | 165 | Failure | Plant Fault - Electrical Equipment |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_014 | Dismissed | Planned | Production unavailability | 2024-12-13T15:41:33+00:00 | 2024-08-27T08:00:00+00:00 | 2024-12-14T20:00:00+00:00 | MW | 165 | 0 | 165 | Failure | Plant Fault - Electrical Equipment |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_013 | Dismissed | Planned | Production unavailability | 2024-12-11T11:57:13+00:00 | 2024-08-27T08:00:00+00:00 | 2024-12-13T20:00:00+00:00 | MW | 165 | 0 | 165 | Failure | Plant Fault - Electrical Equipment |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_012 | Dismissed | Planned | Production unavailability | 2024-12-08T11:09:24+00:00 | 2024-08-27T08:00:00+00:00 | 2024-12-12T08:00:00+00:00 | MW | 165 | 0 | 165 | Failure | Plant Fault - Electrical Equipment |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_011 | Dismissed | Planned | Production unavailability | 2024-12-02T14:08:15+00:00 | 2024-08-27T08:00:00+00:00 | 2024-12-09T08:00:00+00:00 | MW | 165 | 0 | 165 | Failure | Plant Fault - Electrical Equipment |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_010 | Dismissed | Planned | Production unavailability | 2024-11-07T13:57:06+00:00 | 2024-08-27T08:00:00+00:00 | 2024-12-06T12:00:00+00:00 | MW | 165 | 0 | 165 | Failure | Plant Fault - Electrical Equipment |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_009 | Dismissed | Planned | Production unavailability | 2024-11-04T09:17:29+00:00 | 2024-08-27T08:00:00+00:00 | 2024-11-08T12:00:00+00:00 | MW | 165 | 0 | 165 | Failure | Plant Fault - Electrical Equipment |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_008 | Dismissed | Planned | Production unavailability | 2024-10-17T13:44:20+00:00 | 2024-08-27T08:00:00+00:00 | 2024-12-31T18:00:00+00:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Outage Overrun |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_007 | Dismissed | Planned | Production unavailability | 2024-10-03T12:22:29+00:00 | 2024-08-27T08:00:00+00:00 | 2024-10-30T18:00:00+00:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Outage Overrun |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_006 | Dismissed | Planned | Production unavailability | 2024-09-24T09:46:54+00:00 | 2024-08-27T08:00:00+00:00 | 2024-10-30T18:00:00+00:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Outage Overrun |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_005 | Dismissed | Planned | Production unavailability | 2024-09-05T14:06:13+00:00 | 2024-08-27T08:00:00+00:00 | 2024-09-30T18:00:00+00:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Outage Overrun |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_004 | Dismissed | Planned | Production unavailability | 2024-09-02T10:12:00+00:00 | 2024-08-27T08:00:00+00:00 | 2024-09-10T18:00:00+00:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Outage Overrun |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_003 | Dismissed | Planned | Production unavailability | 2024-08-30T17:01:58+00:00 | 2024-08-27T08:00:00+00:00 | 2024-09-03T18:00:00+00:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Outage Overrun |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_002 | Dismissed | Planned | Production unavailability | 2024-08-20T18:07:36+00:00 | 2024-08-27T08:00:00+00:00 | 2024-08-31T08:00:00+00:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000009326_001 | Dismissed | Planned | Production unavailability | 2024-08-06T17:27:13+00:00 | 2024-08-26T07:00:00+00:00 | 2024-08-30T16:00:00+00:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009418_013 | Inactive | Planned | Production unavailability | 2024-12-15T05:02:32+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-15T04:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009419_013 | Inactive | Planned | Production unavailability | 2024-12-15T05:02:32+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-15T04:00:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009420_013 | Inactive | Planned | Production unavailability | 2024-12-15T05:02:32+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-15T04:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009420_012 | Dismissed | Planned | Production unavailability | 2024-12-14T19:27:59+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-15T04:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009419_012 | Dismissed | Planned | Production unavailability | 2024-12-14T19:32:27+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-15T04:00:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009418_012 | Dismissed | Planned | Production unavailability | 2024-12-14T19:26:26+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-15T04:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009418_011 | Dismissed | Planned | Production unavailability | 2024-12-14T12:01:05+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-14T21:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009419_011 | Dismissed | Planned | Production unavailability | 2024-12-14T12:00:15+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-14T21:00:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009420_011 | Dismissed | Planned | Production unavailability | 2024-12-14T11:51:14+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-14T21:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009420_010 | Dismissed | Planned | Production unavailability | 2024-12-13T08:48:33+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-14T17:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009418_010 | Dismissed | Planned | Production unavailability | 2024-12-13T08:48:09+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-14T17:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009419_010 | Dismissed | Planned | Production unavailability | 2024-12-13T08:48:20+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-14T17:00:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009419_009 | Dismissed | Planned | Production unavailability | 2024-12-12T15:52:44+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-13T17:00:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009420_009 | Dismissed | Planned | Production unavailability | 2024-12-12T15:52:57+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-13T17:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009418_009 | Dismissed | Planned | Production unavailability | 2024-12-12T15:52:17+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-13T17:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009419_008 | Dismissed | Planned | Production unavailability | 2024-12-11T23:56:21+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-12T17:00:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009418_008 | Dismissed | Planned | Production unavailability | 2024-12-11T23:57:23+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-12T17:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009420_008 | Dismissed | Planned | Production unavailability | 2024-12-11T23:55:56+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-12T17:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009418_007 | Dismissed | Planned | Production unavailability | 2024-12-08T01:01:24+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-12T05:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009420_007 | Dismissed | Planned | Production unavailability | 2024-12-08T01:03:02+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-12T05:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009419_007 | Dismissed | Planned | Production unavailability | 2024-12-08T01:02:36+00:00 | 2024-12-09T05:00:00+00:00 | 2024-12-12T05:00:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009419_006 | Dismissed | Planned | Production unavailability | 2024-12-05T08:20:08+00:00 | 2024-12-09T08:00:00+00:00 | 2024-12-12T05:00:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009420_006 | Dismissed | Planned | Production unavailability | 2024-12-05T08:19:07+00:00 | 2024-12-09T08:00:00+00:00 | 2024-12-12T05:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009418_006 | Dismissed | Planned | Production unavailability | 2024-12-05T08:22:13+00:00 | 2024-12-09T08:00:00+00:00 | 2024-12-12T05:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009418_005 | Dismissed | Planned | Production unavailability | 2024-12-04T15:15:31+00:00 | 2024-12-09T08:00:00+00:00 | 2024-12-12T00:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009420_005 | Dismissed | Planned | Production unavailability | 2024-12-04T15:18:04+00:00 | 2024-12-09T08:00:00+00:00 | 2024-12-12T00:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009419_005 | Dismissed | Planned | Production unavailability | 2024-12-04T15:17:04+00:00 | 2024-12-09T08:00:00+00:00 | 2024-12-12T00:00:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009420_004 | Dismissed | Planned | Production unavailability | 2024-12-03T11:44:40+00:00 | 2024-12-09T08:00:00+00:00 | 2024-12-11T16:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009419_004 | Dismissed | Planned | Production unavailability | 2024-12-03T11:46:27+00:00 | 2024-12-09T08:00:00+00:00 | 2024-12-11T16:00:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009418_004 | Dismissed | Planned | Production unavailability | 2024-12-03T11:47:48+00:00 | 2024-12-09T08:00:00+00:00 | 2024-12-11T16:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009419_003 | Dismissed | Planned | Production unavailability | 2024-11-04T08:09:37+00:00 | 2024-12-09T08:00:00+00:00 | 2024-12-10T16:00:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009420_003 | Dismissed | Planned | Production unavailability | 2024-11-04T08:10:40+00:00 | 2024-12-09T08:00:00+00:00 | 2024-12-10T16:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009418_003 | Dismissed | Planned | Production unavailability | 2024-11-04T08:08:36+00:00 | 2024-12-09T08:00:00+00:00 | 2024-12-10T16:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
| T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009418_002 | Dismissed | Planned | Production unavailability | 2024-10-03T12:21:00+00:00 | 2024-12-16T08:00:00+00:00 | 2024-12-17T16:00:00+00:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |