This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

SSE Thermal Generation and Gas Storage REMIT information is no longer being updated on this page.
For SSE Thermal Generation and Gas Storage REMIT Information (Unavailability of Facilities and Other Market Information), please visit SSE Thermal REMIT.

Last update at: 2025-12-17T09:30:00+00:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 30 31 32 33 34 >
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_026 Dismissed Planned Production unavailability 2025-04-25T11:02:45+00:00 2024-11-22T09:00:00+00:00 2025-05-06T17:00:00+00:00 MW 26 130 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_025 Dismissed Planned Production unavailability 2025-04-17T10:45:03+00:00 2024-11-22T09:00:00+00:00 2025-04-28T17:00:00+00:00 MW 39 117 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_025 Dismissed Planned Production unavailability 2025-04-17T10:45:17+00:00 2024-11-22T09:00:00+00:00 2025-04-28T17:00:00+00:00 MW 185 117 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_024 Dismissed Planned Production unavailability 2025-04-11T10:56:46+00:00 2024-11-22T09:00:00+00:00 2025-04-22T17:00:00+00:00 MW 39 117 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_024 Dismissed Planned Production unavailability 2025-04-11T10:57:30+00:00 2024-11-22T09:00:00+00:00 2025-04-22T17:00:00+00:00 MW 185 117 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_023 Dismissed Planned Production unavailability 2025-04-04T10:52:57+00:00 2024-11-22T09:00:00+00:00 2025-04-14T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_023 Dismissed Planned Production unavailability 2025-04-04T10:54:45+00:00 2024-11-22T09:00:00+00:00 2025-04-14T17:00:00+00:00 MW 39 117 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_022 Dismissed Planned Production unavailability 2025-04-04T10:52:45+00:00 2024-11-22T09:00:00+00:00 2025-04-14T17:00:00+00:00 MW 26 130 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_022 Dismissed Planned Production unavailability 2025-03-31T10:44:00+00:00 2024-11-22T09:00:00+00:00 2025-04-04T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_021 Dismissed Planned Production unavailability 2025-03-21T10:43:15+00:00 2024-11-22T09:00:00+00:00 2025-03-31T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_021 Dismissed Planned Production unavailability 2025-03-31T10:43:48+00:00 2024-11-22T09:00:00+00:00 2025-04-04T17:00:00+00:00 MW 26 130 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_020 Dismissed Planned Production unavailability 2025-03-21T10:43:03+00:00 2024-11-22T09:00:00+00:00 2025-03-31T17:00:00+00:00 MW 39 117 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_020 Dismissed Planned Production unavailability 2025-03-14T11:19:50+00:00 2024-11-22T09:00:00+00:00 2025-03-21T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_019 Dismissed Planned Production unavailability 2025-03-14T11:19:37+00:00 2024-11-22T09:00:00+00:00 2025-03-21T17:00:00+00:00 MW 39 117 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_019 Dismissed Planned Production unavailability 2025-03-07T10:45:41+00:00 2024-11-22T09:00:00+00:00 2025-03-14T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_018 Dismissed Planned Production unavailability 2025-02-28T12:17:34+00:00 2024-11-22T09:00:00+00:00 2025-03-07T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_018 Dismissed Planned Production unavailability 2025-03-07T10:45:29+00:00 2024-11-22T09:00:00+00:00 2025-03-14T17:00:00+00:00 MW 39 117 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_017 Dismissed Planned Production unavailability 2025-02-28T12:17:16+00:00 2024-11-22T09:00:00+00:00 2025-03-07T17:00:00+00:00 MW 65 91 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_017 Dismissed Planned Production unavailability 2025-02-21T10:48:03+00:00 2024-11-22T09:00:00+00:00 2025-02-28T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_016 Dismissed Planned Production unavailability 2025-02-13T14:34:59+00:00 2024-11-22T09:00:00+00:00 2025-02-24T17:00:00+00:00 MW 224 78 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_016 Dismissed Planned Production unavailability 2025-02-21T10:48:34+00:00 2024-11-22T09:00:00+00:00 2025-02-28T17:00:00+00:00 MW 104 52 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_015 Dismissed Planned Production unavailability 2025-02-13T14:34:18+00:00 2024-11-22T09:00:00+00:00 2025-02-24T17:00:00+00:00 MW 104 52 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_015 Dismissed Planned Production unavailability 2025-02-06T11:02:13+00:00 2024-11-22T09:00:00+00:00 2025-02-17T17:00:00+00:00 MW 224 78 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_014 Dismissed Planned Production unavailability 2025-01-31T12:32:00+00:00 2024-11-22T09:00:00+00:00 2025-02-07T17:00:00+00:00 MW 224 78 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_014 Dismissed Planned Production unavailability 2025-02-06T11:02:33+00:00 2024-11-22T09:00:00+00:00 2025-02-17T17:00:00+00:00 MW 104 52 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_013 Dismissed Planned Production unavailability 2025-01-31T12:30:23+00:00 2024-11-22T09:00:00+00:00 2025-02-07T17:00:00+00:00 MW 104 52 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_013 Dismissed Planned Production unavailability 2025-01-31T12:29:13+00:00 2024-11-22T09:00:00+00:00 2025-02-07T17:00:00+00:00 MW 79 223 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_012 Dismissed Planned Production unavailability 2025-01-31T12:24:30+00:00 2024-11-22T09:00:00+00:00 2025-02-07T17:00:00+00:00 MW 79 233 312 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_012 Dismissed Planned Production unavailability 2025-01-31T12:24:05+00:00 2024-11-22T09:00:00+00:00 2025-02-07T17:00:00+00:00 MW 0 156 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_011 Dismissed Planned Production unavailability 2025-01-31T10:43:44+00:00 2024-11-22T09:00:00+00:00 2025-02-07T17:00:00+00:00 MW 0 39 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_011 Dismissed Planned Production unavailability 2025-01-31T10:42:35+00:00 2024-11-22T09:00:00+00:00 2025-02-07T17:00:00+00:00 MW 79 78 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_010 Dismissed Planned Production unavailability 2025-01-24T10:42:18+00:00 2024-11-22T09:00:00+00:00 2025-01-31T17:00:00+00:00 MW 79 78 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_010 Dismissed Planned Production unavailability 2025-01-24T10:42:03+00:00 2024-11-22T09:00:00+00:00 2025-01-31T17:00:00+00:00 MW 13 26 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_009 Dismissed Planned Production unavailability 2025-01-17T13:07:46+00:00 2024-11-22T09:00:00+00:00 2025-01-24T17:00:00+00:00 MW 13 26 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_009 Dismissed Planned Production unavailability 2025-01-17T13:07:10+00:00 2024-11-22T09:00:00+00:00 2025-01-24T17:00:00+00:00 MW 79 78 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_008 Dismissed Planned Production unavailability 2025-01-10T11:05:23+00:00 2024-11-22T09:00:00+00:00 2025-01-17T17:00:00+00:00 MW 79 78 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_008 Dismissed Planned Production unavailability 2025-01-10T11:05:40+00:00 2024-11-22T09:00:00+00:00 2025-01-17T17:00:00+00:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_007 Dismissed Planned Production unavailability 2025-01-06T10:36:39+00:00 2024-11-22T09:00:00+00:00 2025-01-10T17:00:00+00:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_007 Dismissed Planned Production unavailability 2025-01-06T10:36:26+00:00 2024-11-22T09:00:00+00:00 2025-01-10T17:00:00+00:00 MW 79 78 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_006 Dismissed Planned Production unavailability 2025-01-03T08:32:02+00:00 2024-11-22T09:00:00+00:00 2025-01-07T17:00:00+00:00 MW 79 78 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_006 Dismissed Planned Production unavailability 2025-01-03T08:31:50+00:00 2024-11-22T09:00:00+00:00 2025-01-07T17:00:00+00:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_005 Dismissed Planned Production unavailability 2024-12-20T11:18:30+00:00 2024-11-22T09:00:00+00:00 2025-01-03T17:00:00+00:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_005 Dismissed Planned Production unavailability 2024-12-20T11:18:08+00:00 2024-11-22T09:00:00+00:00 2025-01-03T17:00:00+00:00 MW 79 78 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_004 Dismissed Planned Production unavailability 2024-12-13T10:48:33+00:00 2024-11-22T09:00:00+00:00 2024-12-20T17:00:00+00:00 MW 79 78 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_004 Dismissed Planned Production unavailability 2024-12-13T10:48:19+00:00 2024-11-22T09:00:00+00:00 2024-12-20T17:00:00+00:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_003 Dismissed Planned Production unavailability 2024-12-05T13:07:30+00:00 2024-11-22T09:00:00+00:00 2024-12-13T17:00:00+00:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_003 Dismissed Planned Production unavailability 2024-12-05T13:07:10+00:00 2024-11-22T09:00:00+00:00 2024-12-13T17:00:00+00:00 MW 79 78 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_002 Dismissed Planned Production unavailability 2024-11-29T11:01:13+00:00 2024-11-22T09:00:00+00:00 2024-12-06T17:00:00+00:00 MW 79 78 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_002 Dismissed Planned Production unavailability 2024-11-29T11:00:14+00:00 2024-11-22T09:00:00+00:00 2024-12-05T17:00:00+00:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_001 Dismissed Planned Production unavailability 2024-11-23T08:59:36+00:00 2024-11-22T09:00:00+00:00 2024-11-29T17:00:00+00:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A