This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

SSE Thermal Generation and Gas Storage REMIT information is no longer being updated on this page.
For SSE Thermal Generation and Gas Storage REMIT Information (Unavailability of Facilities and Other Market Information), please visit SSE Thermal REMIT.

Last update at: 2025-12-12T13:00:00+00:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 29 30 31 32 33 >
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000010023_003 Dismissed Planned Consumption unavailability 2025-05-23T15:22:50+00:00 2025-06-06T08:00:00+00:00 2025-06-06T12:00:00+00:00 MW 150 0 150 Foreseen Maintenance
Testing
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000010023_002 Dismissed Planned Consumption unavailability 2025-05-16T12:05:02+00:00 2025-06-06T08:00:00+00:00 2025-06-06T12:00:00+00:00 MW 150 0 150 Foreseen Maintenance
Testing
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000010023_001 Dismissed Planned Consumption unavailability 2025-03-27T14:31:02+00:00 2025-06-04T08:00:00+00:00 2025-06-04T12:00:00+00:00 MW 150 0 150 Foreseen Maintenance
Testing
Hydro Pumped Storage 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000009923_003 Inactive Planned Production unavailability 2025-05-21T14:02:31+00:00 2025-05-21T09:00:00+00:00 2025-05-21T13:00:00+00:00 MW 100 0 100 Foreseen Maintenance
Testing
Hydro Water Reservoir 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000009923_002 Dismissed Planned Production unavailability 2025-02-24T15:11:49+00:00 2025-05-21T09:00:00+00:00 2025-05-21T13:00:00+00:00 MW 100 0 100 Foreseen Maintenance
Testing
Hydro Water Reservoir 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000009923_001 Dismissed Planned Production unavailability 2025-02-24T15:08:12+00:00 2025-05-21T09:00:00+00:00 2025-05-21T13:00:00+00:00 MW 100 0 100 Foreseen Maintenance
Maintenance
Hydro Water Reservoir 10YGB----------A
Yellow River 47W0000000004914
SSE Airtricity Limited
23X--140207ALT-9 0000000000000000000010167_004 Inactive Unplanned Production unavailability 2025-05-21T13:17:31+00:00 2025-05-19T18:05:57+00:00 2025-05-21T12:05:06+00:00 MW 101 0 101 Failure
Commissioning
Wind Onshore 10Y1001A1001A59C
Yellow River 47W0000000004914
SSE Airtricity Limited
23X--140207ALT-9 0000000000000000000010167_003 Dismissed Unplanned Production unavailability 2025-05-21T12:04:18+00:00 2025-05-19T18:05:57+00:00 2025-05-21T12:05:06+00:00 MW 101 0 101 Failure
Commissioning
Wind Onshore 10Y1001A1001A59C
Yellow River 47W0000000004914
SSE Airtricity Limited
23X--140207ALT-9 0000000000000000000010167_002 Dismissed Unplanned Production unavailability 2025-05-20T16:18:24+00:00 2025-05-19T18:05:57+00:00 2025-05-21T17:00:06+00:00 MW 101 0 101 Failure
Commissioning
Wind Onshore 10Y1001A1001A59C
Yellow River 47W0000000004914
SSE Airtricity Limited
23X--140207ALT-9 0000000000000000000010167_001 Dismissed Unplanned Production unavailability 2025-05-19T18:07:19+00:00 2025-05-19T18:05:57+00:00 2025-05-20T17:00:06+00:00 MW 101 0 101 Failure
Commissioning
Wind Onshore 10Y1001A1001A59C
T_STLGW-1 48W00000STLGW-1E
Stronelairg Wind Farm Limited
48X000000000332W 0000000000000000000010146_002 Dismissed Planned Production unavailability 2025-05-20T10:32:30+00:00 2025-07-21T08:00:00+00:00 2025-07-21T16:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_STLGW-1 48W00000STLGW-1E
Stronelairg Wind Farm Limited
48X000000000332W 0000000000000000000010146_001 Dismissed Planned Production unavailability 2025-05-13T09:57:19+00:00 2025-07-21T08:00:00+00:00 2025-07-21T16:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_STLGW-2 48W00000STLGW-2C
Stronelairg Wind Farm Limited
48X000000000332W 0000000000000000000010147_002 Dismissed Planned Production unavailability 2025-05-20T10:32:08+00:00 2025-07-21T08:00:00+00:00 2025-07-21T16:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_STLGW-2 48W00000STLGW-2C
Stronelairg Wind Farm Limited
48X000000000332W 0000000000000000000010147_001 Dismissed Planned Production unavailability 2025-05-13T09:58:39+00:00 2025-07-21T08:00:00+00:00 2025-07-21T16:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
Stronelairg Wind Farm Limited
48X000000000332W 0000000000000000000010148_002 Dismissed Planned Production unavailability 2025-05-20T10:31:12+00:00 2025-07-21T08:00:00+00:00 2025-07-21T16:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
Stronelairg Wind Farm Limited
48X000000000332W 0000000000000000000010148_001 Dismissed Planned Production unavailability 2025-05-13T09:59:52+00:00 2025-07-21T08:00:00+00:00 2025-07-21T16:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000009828_003 Inactive Planned Production unavailability 2025-05-14T14:02:32+00:00 2025-05-14T09:00:00+00:00 2025-05-14T13:00:00+00:00 MW 100 0 100 Foreseen Maintenance
Testing
Hydro Water Reservoir 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000009828_002 Dismissed Planned Production unavailability 2025-01-22T14:28:05+00:00 2025-05-14T09:00:00+00:00 2025-05-14T13:00:00+00:00 MW 100 0 100 Foreseen Maintenance
Testing
Hydro Water Reservoir 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000009828_001 Dismissed Planned Production unavailability 2025-01-22T14:24:27+00:00 2025-05-14T10:00:00+00:00 2025-05-14T12:00:00+00:00 MW 100 0 100 Foreseen Maintenance
Testing
Hydro Water Reservoir 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_028 Inactive Planned Production unavailability 2025-05-13T18:02:32+00:00 2024-11-22T09:00:00+00:00 2025-05-13T17:00:00+00:00 MW 185 117 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_028 Inactive Planned Production unavailability 2025-05-13T18:02:32+00:00 2024-11-22T09:00:00+00:00 2025-05-13T17:00:00+00:00 MW 26 130 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_027 Dismissed Planned Production unavailability 2025-05-02T10:40:55+00:00 2024-11-22T09:00:00+00:00 2025-05-13T17:00:00+00:00 MW 26 130 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_027 Dismissed Planned Production unavailability 2025-05-02T10:40:43+00:00 2024-11-22T09:00:00+00:00 2025-05-13T17:00:00+00:00 MW 185 117 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_026 Dismissed Planned Production unavailability 2025-04-25T11:03:07+00:00 2024-11-22T09:00:00+00:00 2025-05-06T17:00:00+00:00 MW 185 117 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_026 Dismissed Planned Production unavailability 2025-04-25T11:02:45+00:00 2024-11-22T09:00:00+00:00 2025-05-06T17:00:00+00:00 MW 26 130 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_025 Dismissed Planned Production unavailability 2025-04-17T10:45:03+00:00 2024-11-22T09:00:00+00:00 2025-04-28T17:00:00+00:00 MW 39 117 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_025 Dismissed Planned Production unavailability 2025-04-17T10:45:17+00:00 2024-11-22T09:00:00+00:00 2025-04-28T17:00:00+00:00 MW 185 117 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_024 Dismissed Planned Production unavailability 2025-04-11T10:56:46+00:00 2024-11-22T09:00:00+00:00 2025-04-22T17:00:00+00:00 MW 39 117 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_024 Dismissed Planned Production unavailability 2025-04-11T10:57:30+00:00 2024-11-22T09:00:00+00:00 2025-04-22T17:00:00+00:00 MW 185 117 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_023 Dismissed Planned Production unavailability 2025-04-04T10:52:57+00:00 2024-11-22T09:00:00+00:00 2025-04-14T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_023 Dismissed Planned Production unavailability 2025-04-04T10:54:45+00:00 2024-11-22T09:00:00+00:00 2025-04-14T17:00:00+00:00 MW 39 117 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_022 Dismissed Planned Production unavailability 2025-04-04T10:52:45+00:00 2024-11-22T09:00:00+00:00 2025-04-14T17:00:00+00:00 MW 26 130 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_022 Dismissed Planned Production unavailability 2025-03-31T10:44:00+00:00 2024-11-22T09:00:00+00:00 2025-04-04T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_021 Dismissed Planned Production unavailability 2025-03-21T10:43:15+00:00 2024-11-22T09:00:00+00:00 2025-03-31T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_021 Dismissed Planned Production unavailability 2025-03-31T10:43:48+00:00 2024-11-22T09:00:00+00:00 2025-04-04T17:00:00+00:00 MW 26 130 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_020 Dismissed Planned Production unavailability 2025-03-21T10:43:03+00:00 2024-11-22T09:00:00+00:00 2025-03-31T17:00:00+00:00 MW 39 117 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_020 Dismissed Planned Production unavailability 2025-03-14T11:19:50+00:00 2024-11-22T09:00:00+00:00 2025-03-21T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_019 Dismissed Planned Production unavailability 2025-03-14T11:19:37+00:00 2024-11-22T09:00:00+00:00 2025-03-21T17:00:00+00:00 MW 39 117 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_019 Dismissed Planned Production unavailability 2025-03-07T10:45:41+00:00 2024-11-22T09:00:00+00:00 2025-03-14T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_018 Dismissed Planned Production unavailability 2025-02-28T12:17:34+00:00 2024-11-22T09:00:00+00:00 2025-03-07T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_018 Dismissed Planned Production unavailability 2025-03-07T10:45:29+00:00 2024-11-22T09:00:00+00:00 2025-03-14T17:00:00+00:00 MW 39 117 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_017 Dismissed Planned Production unavailability 2025-02-28T12:17:16+00:00 2024-11-22T09:00:00+00:00 2025-03-07T17:00:00+00:00 MW 65 91 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_017 Dismissed Planned Production unavailability 2025-02-21T10:48:03+00:00 2024-11-22T09:00:00+00:00 2025-02-28T17:00:00+00:00 MW 211 91 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_016 Dismissed Planned Production unavailability 2025-02-13T14:34:59+00:00 2024-11-22T09:00:00+00:00 2025-02-24T17:00:00+00:00 MW 224 78 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_016 Dismissed Planned Production unavailability 2025-02-21T10:48:34+00:00 2024-11-22T09:00:00+00:00 2025-02-28T17:00:00+00:00 MW 104 52 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_015 Dismissed Planned Production unavailability 2025-02-13T14:34:18+00:00 2024-11-22T09:00:00+00:00 2025-02-24T17:00:00+00:00 MW 104 52 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_015 Dismissed Planned Production unavailability 2025-02-06T11:02:13+00:00 2024-11-22T09:00:00+00:00 2025-02-17T17:00:00+00:00 MW 224 78 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009653_014 Dismissed Planned Production unavailability 2025-01-31T12:32:00+00:00 2024-11-22T09:00:00+00:00 2025-02-07T17:00:00+00:00 MW 224 78 302 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_014 Dismissed Planned Production unavailability 2025-02-06T11:02:33+00:00 2024-11-22T09:00:00+00:00 2025-02-17T17:00:00+00:00 MW 104 52 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009654_013 Dismissed Planned Production unavailability 2025-01-31T12:30:23+00:00 2024-11-22T09:00:00+00:00 2025-02-07T17:00:00+00:00 MW 104 52 156 Shutdown
Commissioning
Wind Offshore 10YGB----------A