Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 92 93 94 95 96 > | ||||||||||||||||||
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000008312_001 | Dismissed | Planned | Production unavailability | 2023-08-17T03:56:42+01:00 | 2023-08-17T04:00:00+01:00 | 2023-08-17T05:30:00+01:00 | MW | 980 | 200 | 1180 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000008311_002 | Inactive | Planned | Production unavailability | 2023-08-17T05:02:32+01:00 | 2023-08-17T03:15:00+01:00 | 2023-08-17T04:00:00+01:00 | MW | 1080 | 100 | 1180 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000008311_001 | Dismissed | Planned | Production unavailability | 2023-08-17T03:14:34+01:00 | 2023-08-17T03:15:00+01:00 | 2023-08-17T04:00:00+01:00 | MW | 1080 | 100 | 1180 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000008310_005 | Inactive | Unplanned | Production unavailability | 2023-08-17T04:17:32+01:00 | 2023-08-17T01:07:00+01:00 | 2023-08-17T03:15:00+01:00 | MW | 1080 | 100 | 1180 | Failure | Plant Fault - Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000008310_004 | Dismissed | Unplanned | Production unavailability | 2023-08-17T03:15:00+01:00 | 2023-08-17T01:07:00+01:00 | 2023-08-17T03:15:00+01:00 | MW | 1080 | 100 | 1180 | Failure | Plant Fault - Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000008310_003 | Dismissed | Unplanned | Production unavailability | 2023-08-17T02:59:38+01:00 | 2023-08-17T01:07:00+01:00 | 2023-08-17T04:00:00+01:00 | MW | 1080 | 100 | 1180 | Failure | Plant Fault - Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000008310_002 | Dismissed | Unplanned | Production unavailability | 2023-08-17T01:55:30+01:00 | 2023-08-17T01:07:00+01:00 | 2023-08-17T03:05:00+01:00 | MW | 1080 | 100 | 1180 | Failure | Plant Fault - Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000008310_001 | Dismissed | Unplanned | Production unavailability | 2023-08-17T01:08:08+01:00 | 2023-08-17T01:07:00+01:00 | 2023-08-17T02:05:00+01:00 | MW | 1080 | 100 | 1180 | Failure | Plant Fault - Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000008309_002 | Inactive | Unplanned | Production unavailability | 2023-08-16T22:02:32+01:00 | 2023-08-16T18:45:00+01:00 | 2023-08-16T21:00:00+01:00 | MW | 1180 | 0 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000008309_001 | Dismissed | Unplanned | Production unavailability | 2023-08-16T18:45:32+01:00 | 2023-08-16T18:45:00+01:00 | 2023-08-16T21:00:00+01:00 | MW | 1180 | 0 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_019 | Inactive | Planned | Production unavailability | 2023-08-16T18:02:32+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-16T17:00:00+01:00 | MW | 140 | 0 | 140 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_018 | Dismissed | Planned | Production unavailability | 2023-08-15T17:50:00+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-16T17:00:00+01:00 | MW | 140 | 0 | 140 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_018 | Inactive | Planned | Production unavailability | 2023-08-16T18:02:32+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-16T17:00:00+01:00 | MW | 290 | 0 | 290 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_018 | Inactive | Planned | Production unavailability | 2023-08-16T18:02:32+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-16T17:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_017 | Dismissed | Planned | Production unavailability | 2023-08-15T17:52:41+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-16T17:00:00+01:00 | MW | 290 | 0 | 290 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_017 | Dismissed | Planned | Production unavailability | 2023-08-15T17:47:08+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-16T17:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_017 | Dismissed | Planned | Production unavailability | 2023-08-14T17:59:55+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-16T18:00:00+01:00 | MW | 140 | 0 | 140 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_016 | Dismissed | Planned | Production unavailability | 2023-08-14T11:37:26+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-15T18:00:00+01:00 | MW | 140 | 0 | 140 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_016 | Dismissed | Planned | Production unavailability | 2023-08-14T17:59:39+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-16T18:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_016 | Dismissed | Planned | Production unavailability | 2023-08-14T18:00:16+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-16T18:00:00+01:00 | MW | 290 | 0 | 290 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_015 | Dismissed | Planned | Production unavailability | 2023-08-14T11:38:03+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-15T18:00:00+01:00 | MW | 290 | 0 | 290 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_015 | Dismissed | Planned | Production unavailability | 2023-08-14T11:36:44+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-15T18:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_015 | Dismissed | Planned | Production unavailability | 2023-08-11T17:15:14+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-15T12:00:00+01:00 | MW | 140 | 0 | 140 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_014 | Dismissed | Planned | Production unavailability | 2023-08-10T16:57:52+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-12T18:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_014 | Dismissed | Planned | Production unavailability | 2023-08-11T17:13:55+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-15T12:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_014 | Dismissed | Planned | Production unavailability | 2023-08-11T17:16:34+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-15T12:00:00+01:00 | MW | 290 | 0 | 290 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_013 | Dismissed | Planned | Production unavailability | 2023-08-10T16:57:12+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-12T18:00:00+01:00 | MW | 290 | 0 | 290 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_013 | Dismissed | Planned | Production unavailability | 2023-08-10T16:58:18+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-12T18:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_013 | Dismissed | Planned | Production unavailability | 2023-08-01T09:42:59+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-11T17:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_012 | Dismissed | Planned | Production unavailability | 2023-07-26T18:02:34+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-04T17:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_012 | Dismissed | Planned | Production unavailability | 2023-08-01T09:43:56+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-11T17:00:00+01:00 | MW | 290 | 0 | 290 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_012 | Dismissed | Planned | Production unavailability | 2023-08-01T09:42:31+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-11T17:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_011 | Dismissed | Planned | Production unavailability | 2023-07-26T18:03:36+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-04T17:00:00+01:00 | MW | 290 | 0 | 290 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_011 | Dismissed | Planned | Production unavailability | 2023-07-26T18:02:46+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-04T17:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_011 | Dismissed | Planned | Production unavailability | 2023-07-19T17:38:03+01:00 | 2023-07-07T18:00:00+01:00 | 2023-07-28T17:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_010 | Dismissed | Planned | Production unavailability | 2023-07-17T10:49:11+01:00 | 2023-07-07T00:01:00+01:00 | 2023-07-31T23:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_010 | Dismissed | Planned | Production unavailability | 2023-07-26T18:01:42+01:00 | 2023-07-07T18:00:00+01:00 | 2023-08-04T17:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_010 | Dismissed | Planned | Production unavailability | 2023-07-19T17:37:03+01:00 | 2023-07-07T18:00:00+01:00 | 2023-07-28T17:00:00+01:00 | MW | 290 | 0 | 290 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_009 | Dismissed | Planned | Production unavailability | 2023-07-19T16:53:42+01:00 | 2023-07-07T18:00:00+01:00 | 2023-07-21T17:00:00+01:00 | MW | 160 | 130 | 290 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_009 | Dismissed | Planned | Production unavailability | 2023-07-19T17:38:22+01:00 | 2023-07-07T18:00:00+01:00 | 2023-07-28T17:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_009 | Dismissed | Planned | Production unavailability | 2023-07-17T08:58:43+01:00 | 2023-07-07T00:01:00+01:00 | 2023-07-20T23:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_008 | Dismissed | Planned | Production unavailability | 2023-07-13T17:00:59+01:00 | 2023-07-07T00:01:00+01:00 | 2023-07-17T23:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_008 | Dismissed | Planned | Production unavailability | 2023-07-17T17:48:33+01:00 | 2023-07-07T18:00:00+01:00 | 2023-07-21T17:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_008 | Dismissed | Planned | Production unavailability | 2023-07-17T17:50:06+01:00 | 2023-07-07T18:00:00+01:00 | 2023-07-21T17:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_007 | Dismissed | Planned | Production unavailability | 2023-07-17T08:59:44+01:00 | 2023-07-07T18:00:00+01:00 | 2023-07-20T23:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_007 | Dismissed | Planned | Production unavailability | 2023-07-17T08:58:10+01:00 | 2023-07-07T18:00:00+01:00 | 2023-07-20T23:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_007 | Dismissed | Planned | Production unavailability | 2023-07-13T08:51:07+01:00 | 2023-07-07T00:01:00+01:00 | 2023-07-14T23:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008220_006 | Dismissed | Planned | Production unavailability | 2023-07-12T08:57:29+01:00 | 2023-07-07T00:01:00+01:00 | 2023-07-13T23:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008233_006 | Dismissed | Planned | Production unavailability | 2023-07-13T17:02:05+01:00 | 2023-07-07T18:00:00+01:00 | 2023-07-17T23:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008234_006 | Dismissed | Planned | Production unavailability | 2023-07-13T17:00:37+01:00 | 2023-07-07T18:00:00+01:00 | 2023-07-17T23:00:00+01:00 | MW | 160 | 0 | 160 | Shutdown | Commissioning |