Last update at: 2024-09-24T10:00:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 82 83 84 85 86 > | ||||||||||||||||||
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008460_002 | Inactive | Planned | Production unavailability | 2023-09-29T13:03:45+01:00 | 2023-09-29T09:01:00+01:00 | 2023-09-29T13:01:00+01:00 | MW | 150 | 208 | 358 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008460_001 | Dismissed | Planned | Production unavailability | 2023-09-28T20:57:26+01:00 | 2023-09-29T09:01:00+01:00 | 2023-10-01T17:00:00+01:00 | MW | 150 | 208 | 358 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_021 | Inactive | Planned | Production unavailability | 2023-09-29T10:02:32+01:00 | 2023-06-03T14:26:00+01:00 | 2023-09-29T09:00:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_020 | Dismissed | Planned | Production unavailability | 2023-09-28T18:22:04+01:00 | 2023-06-03T14:26:00+01:00 | 2023-09-29T09:00:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_019 | Dismissed | Planned | Production unavailability | 2023-09-28T12:42:29+01:00 | 2023-06-03T14:26:00+01:00 | 2023-09-29T18:00:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_018 | Dismissed | Planned | Production unavailability | 2023-09-25T11:12:05+01:00 | 2023-06-03T14:26:00+01:00 | 2023-09-29T12:00:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_017 | Dismissed | Planned | Production unavailability | 2023-07-19T17:39:26+01:00 | 2023-06-03T14:26:00+01:00 | 2023-09-29T12:00:00+01:00 | MW | 300 | 0 | 300 | Failure | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_016 | Dismissed | Planned | Production unavailability | 2023-06-23T17:20:51+01:00 | 2023-06-03T14:26:00+01:00 | 2023-08-07T12:00:00+01:00 | MW | 300 | 0 | 300 | Failure | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_015 | Dismissed | Planned | Production unavailability | 2023-06-10T02:58:24+01:00 | 2023-06-03T14:26:00+01:00 | 2023-07-07T12:00:00+01:00 | MW | 300 | 0 | 300 | Failure | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_014 | Dismissed | Planned | Production unavailability | 2023-06-09T15:32:19+01:00 | 2023-06-03T14:00:00+01:00 | 2023-07-07T12:00:00+01:00 | MW | 300 | 0 | 300 | Failure | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_013 | Dismissed | Planned | Production unavailability | 2023-06-03T14:22:21+01:00 | 2023-06-03T14:00:00+01:00 | 2023-06-16T05:59:00+01:00 | MW | 300 | 0 | 300 | Failure | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_012 | Dismissed | Planned | Production unavailability | 2023-06-03T14:15:37+01:00 | 2023-06-03T14:00:00+01:00 | 2023-06-16T05:59:00+01:00 | MW | 300 | 0 | 300 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_011 | Dismissed | Planned | Production unavailability | 2023-05-26T09:13:37+01:00 | 2023-05-26T12:30:00+01:00 | 2023-06-16T05:59:00+01:00 | MW | 220 | 80 | 300 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_010 | Dismissed | Planned | Production unavailability | 2023-05-24T11:32:12+01:00 | 2023-05-28T13:00:00+01:00 | 2023-06-16T05:59:00+01:00 | MW | 220 | 80 | 300 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_009 | Dismissed | Planned | Production unavailability | 2023-05-24T10:03:14+01:00 | 2023-06-04T00:00:00+01:00 | 2023-06-16T05:59:00+01:00 | MW | 220 | 80 | 300 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_008 | Dismissed | Planned | Production unavailability | 2023-05-22T17:49:42+01:00 | 2023-05-25T13:00:00+01:00 | 2023-06-06T05:59:00+01:00 | MW | 220 | 80 | 300 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008168_008 | Inactive | Planned | Production unavailability | 2023-09-29T10:02:32+01:00 | 2023-06-03T14:26:00+01:00 | 2023-09-29T09:00:00+01:00 | MW | 80 | 0 | 80 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008168_007 | Dismissed | Planned | Production unavailability | 2023-09-28T18:31:51+01:00 | 2023-06-03T14:26:00+01:00 | 2023-09-29T09:00:00+01:00 | MW | 80 | 0 | 80 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_007 | Dismissed | Planned | Production unavailability | 2023-05-19T17:14:47+01:00 | 2023-05-23T13:00:00+01:00 | 2023-06-06T05:59:00+01:00 | MW | 220 | 80 | 300 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_006 | Dismissed | Planned | Production unavailability | 2023-05-16T13:29:32+01:00 | 2023-05-23T14:00:00+01:00 | 2023-06-06T05:59:00+01:00 | MW | 220 | 80 | 300 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008168_006 | Dismissed | Planned | Production unavailability | 2023-09-28T12:36:03+01:00 | 2023-06-03T14:26:00+01:00 | 2023-09-29T18:00:00+01:00 | MW | 80 | 0 | 80 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008168_005 | Dismissed | Planned | Production unavailability | 2023-09-25T11:13:55+01:00 | 2023-06-03T14:26:00+01:00 | 2023-09-29T12:00:00+01:00 | MW | 80 | 0 | 80 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_005 | Dismissed | Planned | Production unavailability | 2023-04-22T12:05:33+01:00 | 2023-04-23T12:01:00+01:00 | 2023-06-06T05:59:00+01:00 | MW | 220 | 80 | 300 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_004 | Dismissed | Planned | Production unavailability | 2023-04-19T11:50:16+01:00 | 2023-04-23T14:01:00+01:00 | 2023-06-06T05:59:00+01:00 | MW | 220 | 80 | 300 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008168_004 | Dismissed | Planned | Production unavailability | 2023-07-19T17:39:02+01:00 | 2023-06-03T14:26:00+01:00 | 2023-09-29T12:00:00+01:00 | MW | 80 | 0 | 80 | Failure | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008168_003 | Dismissed | Planned | Production unavailability | 2023-06-23T17:21:18+01:00 | 2023-06-03T14:26:00+01:00 | 2023-08-07T12:00:00+01:00 | MW | 80 | 0 | 80 | Failure | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_003 | Dismissed | Planned | Production unavailability | 2023-04-13T17:36:27+01:00 | 2023-04-23T14:01:00+01:00 | 2023-05-11T05:59:00+01:00 | MW | 220 | 80 | 300 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_002 | Dismissed | Planned | Production unavailability | 2023-04-05T16:27:14+01:00 | 2023-04-23T16:01:00+01:00 | 2023-05-11T05:59:00+01:00 | MW | 220 | 80 | 300 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008168_002 | Dismissed | Planned | Production unavailability | 2023-06-09T15:37:41+01:00 | 2023-06-03T14:26:00+01:00 | 2023-07-07T12:00:00+01:00 | MW | 80 | 0 | 80 | Failure | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008168_001 | Dismissed | Planned | Production unavailability | 2023-06-03T14:18:18+01:00 | 2023-06-03T14:00:00+01:00 | 2023-06-16T05:59:00+01:00 | MW | 80 | 0 | 80 | Failure | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008067_001 | Dismissed | Planned | Production unavailability | 2023-04-05T16:22:38+01:00 | 2023-04-23T16:01:00+01:00 | 2023-05-11T05:59:00+01:00 | MW | 220 | 80 | 300 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_CLDNW-1 | 48W00000CLDNW-1Q | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008461_003 | Inactive | Unplanned | Production unavailability | 2023-09-29T09:02:32+01:00 | 2023-09-28T23:02:00+01:00 | 2023-09-29T07:55:00+01:00 | MW | 101 | 86 | 187 | Shutdown | Plant Fault - Electrical Equipment |
Wind Onshore | 10YGB----------A |
T_CLDNW-1 | 48W00000CLDNW-1Q | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008461_002 | Dismissed | Unplanned | Production unavailability | 2023-09-29T07:54:07+01:00 | 2023-09-28T23:02:00+01:00 | 2023-09-29T07:55:00+01:00 | MW | 101 | 86 | 187 | Shutdown | Plant Fault - Electrical Equipment |
Wind Onshore | 10YGB----------A |
T_CLDNW-1 | 48W00000CLDNW-1Q | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008461_001 | Dismissed | Unplanned | Production unavailability | 2023-09-28T23:04:06+01:00 | 2023-09-28T23:02:00+01:00 | 2023-09-29T09:00:00+01:00 | MW | 101 | 86 | 187 | Shutdown | Plant Fault - Electrical Equipment |
Wind Onshore | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000008298_004 | Inactive | Planned | Production unavailability | 2023-09-29T01:02:39+01:00 | 2023-09-25T06:00:00+01:00 | 2023-09-28T23:59:00+01:00 | MW | 710 | 0 | 710 | Failure | Grid |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000008298_003 | Dismissed | Planned | Production unavailability | 2023-09-27T16:28:00+01:00 | 2023-09-25T06:00:00+01:00 | 2023-09-28T23:59:00+01:00 | MW | 710 | 0 | 710 | Failure | Grid |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000008298_002 | Dismissed | Planned | Production unavailability | 2023-09-26T12:18:45+01:00 | 2023-09-25T06:00:00+01:00 | 2023-09-27T23:59:00+01:00 | MW | 710 | 0 | 710 | Failure | Grid |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000008298_001 | Dismissed | Planned | Production unavailability | 2023-08-09T12:21:30+01:00 | 2023-09-25T06:00:00+01:00 | 2023-09-27T23:59:00+01:00 | MW | 370 | 340 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000008273_002 | Dismissed | Planned | Production unavailability | 2023-09-28T17:33:01+01:00 | 2024-02-10T06:00:00+00:00 | 2024-02-13T23:59:00+00:00 | MW | 370 | 340 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000008273_001 | Dismissed | Planned | Production unavailability | 2023-07-28T16:34:00+01:00 | 2024-02-10T06:00:00+00:00 | 2024-02-13T23:59:00+00:00 | MW | 370 | 340 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008447_010 | Inactive | Planned | Consumption unavailability | 2023-09-27T16:02:32+01:00 | 2023-09-24T20:00:00+01:00 | 2023-09-27T15:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008447_009 | Dismissed | Planned | Consumption unavailability | 2023-09-27T11:32:32+01:00 | 2023-09-24T20:00:00+01:00 | 2023-09-27T15:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008447_008 | Dismissed | Planned | Consumption unavailability | 2023-09-26T17:38:31+01:00 | 2023-09-24T20:00:00+01:00 | 2023-09-27T12:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008447_007 | Dismissed | Planned | Consumption unavailability | 2023-09-26T12:34:55+01:00 | 2023-09-24T20:00:00+01:00 | 2023-09-26T18:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008447_006 | Dismissed | Planned | Consumption unavailability | 2023-09-26T11:19:39+01:00 | 2023-09-24T20:00:00+01:00 | 2023-09-26T15:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Plant Fault - Generator |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008447_005 | Dismissed | Planned | Consumption unavailability | 2023-09-26T08:23:51+01:00 | 2023-09-24T20:00:00+01:00 | 2023-09-26T12:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Plant Fault - Generator |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008447_004 | Dismissed | Planned | Consumption unavailability | 2023-09-26T08:22:04+01:00 | 2023-09-24T20:00:00+01:00 | 2023-09-26T12:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008447_003 | Dismissed | Planned | Consumption unavailability | 2023-09-25T19:53:35+01:00 | 2023-09-24T20:00:00+01:00 | 2023-09-26T09:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008447_002 | Dismissed | Planned | Consumption unavailability | 2023-09-25T10:56:16+01:00 | 2023-09-24T20:00:00+01:00 | 2023-09-25T21:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008447_001 | Dismissed | Planned | Consumption unavailability | 2023-09-24T19:55:20+01:00 | 2023-09-24T20:00:00+01:00 | 2023-09-25T12:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |