Last update at: 2024-09-23T21:30:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 76 77 78 79 80 > | ||||||||||||||||||
T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000008392_001 | Dismissed | Planned | Production unavailability | 2023-09-07T15:37:42+01:00 | 2023-10-17T09:00:00+01:00 | 2023-10-17T16:00:00+01:00 | MW | 100 | 0 | 100 | Foreseen Maintenance | Maintenance |
Hydro Water Reservoir | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008500_004 | Inactive | Planned | Consumption unavailability | 2023-10-15T19:02:31+01:00 | 2023-10-15T04:48:00+01:00 | 2023-10-15T18:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008500_003 | Dismissed | Planned | Consumption unavailability | 2023-10-15T10:27:15+01:00 | 2023-10-15T04:48:00+01:00 | 2023-10-15T18:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008500_002 | Dismissed | Planned | Consumption unavailability | 2023-10-15T09:38:50+01:00 | 2023-10-15T04:48:00+01:00 | 2023-10-15T13:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008500_001 | Dismissed | Planned | Consumption unavailability | 2023-10-15T04:18:20+01:00 | 2023-10-15T04:48:00+01:00 | 2023-10-15T11:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008499_003 | Inactive | Planned | Production unavailability | 2023-10-15T13:02:32+01:00 | 2023-10-15T06:00:00+01:00 | 2023-10-15T12:00:00+01:00 | MW | 755 | 0 | 755 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008499_002 | Dismissed | Planned | Production unavailability | 2023-10-15T11:58:25+01:00 | 2023-10-15T06:00:00+01:00 | 2023-10-15T12:00:00+01:00 | MW | 755 | 0 | 755 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008499_001 | Dismissed | Planned | Production unavailability | 2023-10-15T00:31:42+01:00 | 2023-10-15T06:00:00+01:00 | 2023-10-15T14:00:00+01:00 | MW | 755 | 0 | 755 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008417_008 | Inactive | Planned | Production unavailability | 2023-10-14T20:02:32+01:00 | 2023-10-11T08:01:00+01:00 | 2023-10-14T19:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008417_007 | Dismissed | Planned | Production unavailability | 2023-10-09T17:27:29+01:00 | 2023-10-11T08:01:00+01:00 | 2023-10-14T19:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008417_006 | Dismissed | Planned | Production unavailability | 2023-10-06T15:43:20+01:00 | 2023-10-10T12:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008415_006 | Inactive | Planned | Production unavailability | 2023-10-14T20:02:32+01:00 | 2023-10-11T08:01:00+01:00 | 2023-10-14T19:00:00+01:00 | MW | 138 | 0 | 138 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008458_006 | Inactive | Planned | Production unavailability | 2023-10-14T20:02:32+01:00 | 2023-10-11T08:01:00+01:00 | 2023-10-14T19:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008458_005 | Dismissed | Planned | Production unavailability | 2023-10-09T17:22:07+01:00 | 2023-10-11T08:01:00+01:00 | 2023-10-14T19:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008415_005 | Dismissed | Planned | Production unavailability | 2023-10-09T17:24:23+01:00 | 2023-10-11T08:01:00+01:00 | 2023-10-14T19:00:00+01:00 | MW | 138 | 0 | 138 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008417_005 | Dismissed | Planned | Production unavailability | 2023-10-06T15:42:57+01:00 | 2023-10-10T12:00:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008417_004 | Dismissed | Planned | Production unavailability | 2023-09-29T10:21:44+01:00 | 2023-10-09T08:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008415_004 | Dismissed | Planned | Production unavailability | 2023-10-06T15:41:36+01:00 | 2023-10-10T12:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 138 | 0 | 138 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008458_004 | Dismissed | Planned | Production unavailability | 2023-10-06T15:40:09+01:00 | 2023-10-10T12:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008458_003 | Dismissed | Planned | Production unavailability | 2023-10-05T17:07:11+01:00 | 2023-10-09T08:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008415_003 | Dismissed | Planned | Production unavailability | 2023-09-25T11:19:23+01:00 | 2023-10-09T08:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 138 | 0 | 138 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008417_003 | Dismissed | Planned | Production unavailability | 2023-09-25T11:21:00+01:00 | 2023-10-09T08:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 120 | 0 | 120 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008417_002 | Dismissed | Planned | Production unavailability | 2023-09-15T15:50:23+01:00 | 2023-10-09T08:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 120 | 0 | 120 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008415_002 | Dismissed | Planned | Production unavailability | 2023-09-15T15:50:49+01:00 | 2023-10-09T08:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 138 | 0 | 138 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008458_002 | Dismissed | Planned | Production unavailability | 2023-09-29T10:21:21+01:00 | 2023-10-09T08:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 100 | 40 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008458_001 | Dismissed | Planned | Production unavailability | 2023-09-28T18:47:55+01:00 | 2023-10-09T08:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 100 | 0 | 100 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008415_001 | Dismissed | Planned | Production unavailability | 2023-09-15T12:50:03+01:00 | 2023-10-09T08:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008417_001 | Dismissed | Planned | Production unavailability | 2023-09-15T12:56:38+01:00 | 2023-10-09T08:01:00+01:00 | 2023-10-13T18:00:00+01:00 | MW | 300 | 0 | 300 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008498_003 | Inactive | Planned | Production unavailability | 2023-10-14T16:02:32+01:00 | 2023-10-14T08:00:00+01:00 | 2023-10-14T15:00:00+01:00 | MW | 755 | 0 | 755 | Foreseen Maintenance | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008498_002 | Dismissed | Planned | Production unavailability | 2023-10-14T14:45:56+01:00 | 2023-10-14T08:00:00+01:00 | 2023-10-14T15:00:00+01:00 | MW | 755 | 0 | 755 | Foreseen Maintenance | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008498_001 | Dismissed | Planned | Production unavailability | 2023-10-13T17:33:05+01:00 | 2023-10-14T08:00:00+01:00 | 2023-10-14T23:00:00+01:00 | MW | 755 | 0 | 755 | Foreseen Maintenance | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_021 | Dismissed | Planned | Production unavailability | 2023-10-12T11:23:27+01:00 | 2023-10-08T00:01:00+01:00 | 2023-10-12T11:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_020 | Dismissed | Planned | Production unavailability | 2023-10-12T10:58:12+01:00 | 2023-10-08T00:01:00+01:00 | 2023-10-12T11:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_019 | Dismissed | Planned | Production unavailability | 2023-10-10T17:00:01+01:00 | 2023-10-08T00:01:00+01:00 | 2023-10-12T17:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_018 | Dismissed | Planned | Production unavailability | 2023-10-09T17:11:14+01:00 | 2023-10-08T00:01:00+01:00 | 2023-10-11T17:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_017 | Dismissed | Planned | Production unavailability | 2023-10-07T23:11:43+01:00 | 2023-10-08T00:01:00+01:00 | 2023-10-10T17:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_016 | Dismissed | Planned | Production unavailability | 2023-10-06T21:23:54+01:00 | 2023-10-09T20:01:00+01:00 | 2023-10-10T17:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_015 | Dismissed | Planned | Production unavailability | 2023-10-06T20:28:57+01:00 | 2023-10-07T20:01:00+01:00 | 2023-10-10T17:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_014 | Dismissed | Planned | Production unavailability | 2023-10-06T17:02:08+01:00 | 2023-10-06T20:01:00+01:00 | 2023-10-10T17:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_013 | Dismissed | Planned | Production unavailability | 2023-10-06T15:31:09+01:00 | 2023-10-06T19:01:00+01:00 | 2023-10-10T17:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_012 | Dismissed | Planned | Production unavailability | 2023-10-05T17:05:34+01:00 | 2023-10-06T17:01:00+01:00 | 2023-10-10T17:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_011 | Dismissed | Planned | Production unavailability | 2023-10-04T17:32:50+01:00 | 2023-10-06T14:01:00+01:00 | 2023-10-10T17:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_010 | Dismissed | Planned | Production unavailability | 2023-10-04T17:32:17+01:00 | 2023-10-06T14:01:00+01:00 | 2023-10-10T12:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_009 | Dismissed | Planned | Production unavailability | 2023-10-01T11:35:32+01:00 | 2023-10-06T17:01:00+01:00 | 2023-10-10T12:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_008 | Dismissed | Planned | Production unavailability | 2023-09-30T14:25:44+01:00 | 2023-10-01T17:01:00+01:00 | 2023-10-06T12:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_007 | Dismissed | Planned | Production unavailability | 2023-09-30T12:34:52+01:00 | 2023-09-30T17:01:00+01:00 | 2023-10-06T12:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_006 | Dismissed | Planned | Production unavailability | 2023-09-28T18:30:35+01:00 | 2023-09-30T15:01:00+01:00 | 2023-10-06T12:00:00+01:00 | MW | 100 | 200 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_005 | Dismissed | Planned | Production unavailability | 2023-09-28T12:48:56+01:00 | 2023-09-29T18:01:00+01:00 | 2023-10-04T12:00:00+01:00 | MW | 90 | 210 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_004 | Dismissed | Planned | Production unavailability | 2023-09-25T12:17:43+01:00 | 2023-09-29T12:01:00+01:00 | 2023-10-04T12:00:00+01:00 | MW | 90 | 210 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008410_003 | Dismissed | Planned | Production unavailability | 2023-09-25T11:15:04+01:00 | 2023-09-29T12:01:00+01:00 | 2023-10-04T12:00:00+01:00 | MW | 90 | 210 | 300 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |