Last update at: 2024-09-25T03:00:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 104 105 106 107 108 > | ||||||||||||||||||
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008157_001 | Dismissed | Planned | Consumption unavailability | 2023-05-27T11:43:45+01:00 | 2023-05-27T16:00:00+01:00 | 2023-05-27T22:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008158_004 | Inactive | Planned | Consumption unavailability | 2023-05-28T02:02:32+01:00 | 2023-05-27T18:30:00+01:00 | 2023-05-28T01:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008158_003 | Dismissed | Planned | Consumption unavailability | 2023-05-27T16:43:45+01:00 | 2023-05-27T18:30:00+01:00 | 2023-05-28T01:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008158_002 | Dismissed | Planned | Consumption unavailability | 2023-05-27T13:25:41+01:00 | 2023-05-27T18:00:00+01:00 | 2023-05-27T22:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008158_001 | Dismissed | Planned | Consumption unavailability | 2023-05-27T11:44:45+01:00 | 2023-05-27T15:00:00+01:00 | 2023-05-27T22:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008128_008 | Inactive | Planned | Production unavailability | 2023-05-26T14:02:32+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-26T12:59:00+01:00 | MW | 28 | 330 | 358 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008128_007 | Dismissed | Planned | Production unavailability | 2023-05-26T09:29:08+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-26T12:59:00+01:00 | MW | 28 | 330 | 358 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008128_006 | Dismissed | Planned | Production unavailability | 2023-05-24T11:35:23+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-28T12:59:00+01:00 | MW | 28 | 330 | 358 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008143_006 | Inactive | Planned | Production unavailability | 2023-05-26T14:02:32+01:00 | 2023-05-21T12:01:00+01:00 | 2023-05-26T12:59:00+01:00 | MW | 100 | 40 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008143_005 | Dismissed | Planned | Production unavailability | 2023-05-26T09:21:06+01:00 | 2023-05-21T12:01:00+01:00 | 2023-05-26T12:59:00+01:00 | MW | 100 | 40 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008128_005 | Dismissed | Planned | Production unavailability | 2023-05-24T10:06:56+01:00 | 2023-05-16T13:20:00+01:00 | 2023-06-04T12:59:00+01:00 | MW | 28 | 330 | 358 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008128_004 | Dismissed | Planned | Production unavailability | 2023-05-22T17:47:12+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-25T13:59:00+01:00 | MW | 28 | 330 | 358 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008143_004 | Dismissed | Planned | Production unavailability | 2023-05-24T11:33:15+01:00 | 2023-05-21T12:01:00+01:00 | 2023-05-28T12:59:00+01:00 | MW | 100 | 40 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008143_003 | Dismissed | Planned | Production unavailability | 2023-05-24T10:04:35+01:00 | 2023-05-21T12:01:00+01:00 | 2023-06-04T12:59:00+01:00 | MW | 100 | 40 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008128_003 | Dismissed | Planned | Production unavailability | 2023-05-17T11:50:30+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-23T13:59:00+01:00 | MW | 28 | 330 | 358 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008143_002 | Dismissed | Planned | Production unavailability | 2023-05-22T17:48:30+01:00 | 2023-05-21T12:01:00+01:00 | 2023-05-25T12:59:00+01:00 | MW | 100 | 40 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008128_002 | Dismissed | Planned | Production unavailability | 2023-05-16T23:12:46+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-18T08:59:00+01:00 | MW | 28 | 330 | 358 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008128_001 | Dismissed | Planned | Production unavailability | 2023-05-16T13:18:26+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-23T13:59:00+01:00 | MW | 28 | 330 | 358 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008143_001 | Dismissed | Planned | Production unavailability | 2023-05-19T17:21:03+01:00 | 2023-05-21T12:01:00+01:00 | 2023-05-23T12:59:00+01:00 | MW | 100 | 40 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008126_008 | Inactive | Unplanned | Production unavailability | 2023-05-26T13:32:32+01:00 | 2023-05-16T12:29:00+01:00 | 2023-05-26T12:29:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008126_007 | Dismissed | Unplanned | Production unavailability | 2023-05-26T09:12:41+01:00 | 2023-05-16T12:29:00+01:00 | 2023-05-26T12:29:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008126_006 | Dismissed | Unplanned | Production unavailability | 2023-05-24T11:30:29+01:00 | 2023-05-16T10:53:00+01:00 | 2023-05-28T12:59:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008126_005 | Dismissed | Unplanned | Production unavailability | 2023-05-24T10:02:16+01:00 | 2023-05-16T10:53:00+01:00 | 2023-06-04T12:59:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008126_004 | Dismissed | Unplanned | Production unavailability | 2023-05-22T17:49:56+01:00 | 2023-05-16T10:53:00+01:00 | 2023-05-25T12:59:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008126_003 | Dismissed | Unplanned | Production unavailability | 2023-05-19T17:14:23+01:00 | 2023-05-16T10:53:00+01:00 | 2023-05-23T12:59:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008126_002 | Dismissed | Unplanned | Production unavailability | 2023-05-16T13:28:25+01:00 | 2023-05-16T10:53:00+01:00 | 2023-05-23T13:59:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008126_001 | Dismissed | Unplanned | Production unavailability | 2023-05-16T10:54:32+01:00 | 2023-05-16T10:53:00+01:00 | 2023-05-17T11:00:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_BEATO-4 | 48W00000BEATO-4N | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000007983_003 | Dismissed | Planned | Production unavailability | 2023-05-25T09:55:38+01:00 | 2023-10-22T08:00:00+01:00 | 2023-10-31T18:00:00+00:00 | MW | 168 | 0 | 168 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_BEATO-4 | 48W00000BEATO-4N | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000007983_002 | Dismissed | Planned | Production unavailability | 2023-05-25T08:41:14+01:00 | 2023-10-22T08:00:00+01:00 | 2023-10-31T18:00:00+00:00 | MW | 168 | 0 | 168 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_BEATO-4 | 48W00000BEATO-4N | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000007983_001 | Dismissed | Planned | Production unavailability | 2023-02-23T12:55:13+00:00 | 2023-09-11T08:00:00+01:00 | 2023-09-30T16:00:00+01:00 | MW | 168 | 0 | 168 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_BEATO-2 | 48W00000BEATO-2R | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000007982_003 | Dismissed | Planned | Production unavailability | 2023-05-25T09:53:49+01:00 | 2023-10-22T08:00:00+01:00 | 2023-10-31T18:00:00+00:00 | MW | 126 | 0 | 126 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_BEATO-2 | 48W00000BEATO-2R | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000007982_002 | Dismissed | Planned | Production unavailability | 2023-05-25T08:44:28+01:00 | 2023-10-22T08:00:00+01:00 | 2023-10-31T18:00:00+00:00 | MW | 126 | 0 | 126 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_BEATO-2 | 48W00000BEATO-2R | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000007982_001 | Dismissed | Planned | Production unavailability | 2023-02-23T12:52:47+00:00 | 2023-09-11T08:00:00+01:00 | 2023-09-30T16:00:00+01:00 | MW | 126 | 0 | 126 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008146_002 | Inactive | Planned | Consumption unavailability | 2023-05-24T16:02:32+01:00 | 2023-05-24T04:45:00+01:00 | 2023-05-24T15:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008146_001 | Dismissed | Planned | Consumption unavailability | 2023-05-24T03:17:24+01:00 | 2023-05-24T04:45:00+01:00 | 2023-05-24T15:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008147_003 | Inactive | Planned | Consumption unavailability | 2023-05-24T12:02:32+01:00 | 2023-05-24T04:30:00+01:00 | 2023-05-24T11:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008147_002 | Dismissed | Planned | Consumption unavailability | 2023-05-24T10:40:17+01:00 | 2023-05-24T04:30:00+01:00 | 2023-05-24T11:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008147_001 | Dismissed | Planned | Consumption unavailability | 2023-05-24T03:38:06+01:00 | 2023-05-24T04:30:00+01:00 | 2023-05-24T15:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008129_004 | Inactive | Planned | Production unavailability | 2023-05-23T15:02:32+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-23T13:59:00+01:00 | MW | 0 | 80 | 80 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008129_003 | Dismissed | Planned | Production unavailability | 2023-05-17T11:43:39+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-23T13:59:00+01:00 | MW | 0 | 80 | 80 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008129_002 | Dismissed | Planned | Production unavailability | 2023-05-16T23:29:16+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-18T08:59:00+01:00 | MW | 0 | 80 | 80 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008129_001 | Dismissed | Planned | Production unavailability | 2023-05-16T13:26:05+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-23T13:59:00+01:00 | MW | 0 | 80 | 80 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008137_006 | Inactive | Planned | Production unavailability | 2023-05-22T01:02:32+01:00 | 2023-05-17T22:00:00+01:00 | 2023-05-22T00:01:00+01:00 | MW | 405 | 350 | 755 | Failure | Plant Fault - Boiler |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008137_005 | Dismissed | Planned | Production unavailability | 2023-05-17T12:06:25+01:00 | 2023-05-17T22:00:00+01:00 | 2023-05-22T00:01:00+01:00 | MW | 405 | 350 | 755 | Failure | Plant Fault - Boiler |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008137_004 | Dismissed | Planned | Production unavailability | 2023-05-17T11:59:14+01:00 | 2023-05-17T22:00:00+01:00 | 2023-05-21T23:01:00+01:00 | MW | 405 | 350 | 755 | Failure | Plant Fault - Boiler |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008137_003 | Dismissed | Planned | Production unavailability | 2023-05-17T11:58:22+01:00 | 2023-05-17T22:00:00+01:00 | 2023-05-21T23:59:00+01:00 | MW | 405 | 350 | 755 | Failure | Plant Fault - Boiler |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008137_002 | Dismissed | Planned | Production unavailability | 2023-05-17T11:57:30+01:00 | 2023-05-17T22:00:00+01:00 | 2023-05-20T23:59:00+01:00 | MW | 405 | 350 | 755 | Failure | Plant Fault - Boiler |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008137_001 | Dismissed | Planned | Production unavailability | 2023-05-17T11:49:21+01:00 | 2023-05-17T22:00:00+01:00 | 2023-05-19T23:59:00+01:00 | MW | 405 | 350 | 755 | Failure | Plant Fault - Boiler |
Fossil Gas | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008142_002 | Inactive | Planned | Production unavailability | 2023-05-21T13:02:32+01:00 | 2023-04-06T16:01:00+01:00 | 2023-05-21T12:00:00+01:00 | MW | 60 | 80 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008142_001 | Dismissed | Planned | Production unavailability | 2023-05-19T17:19:44+01:00 | 2023-04-06T16:01:00+01:00 | 2023-05-21T12:00:00+01:00 | MW | 60 | 80 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |