Last update at: 2026-04-02T15:30:00+00:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
| Market Participant | Market Participant Code | Unit Location | Unit Name | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
|---|---|---|---|---|---|---|---|---|---|
| 1 2 3 4 5 > | |||||||||
SSE GENERATION |
48X000000000077M | Other_0000000000000010910_002 | Active | 2026-04-02T15:29:54+00:00 | 2026-04-01T17:15:00+00:00 | 2026-04-06T13:00:00+00:00 | Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010910_001 | Dismissed | 2026-04-01T16:14:13+00:00 | 2026-04-01T17:15:00+00:00 | 2026-04-03T17:00:00+00:00 | Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010897_003 | Dismissed | 2026-04-01T16:12:16+00:00 | 2026-04-01T08:00:00+00:00 | 2026-04-01T17:15:00+00:00 | Planned Maintenance will result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010897_002 | Dismissed | 2026-04-01T09:44:35+00:00 | 2026-04-01T08:00:00+00:00 | 2026-04-02T16:00:00+00:00 | Planned Maintenance will result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010897_001 | Dismissed | 2026-03-26T11:09:42+00:00 | 2026-04-01T08:00:00+00:00 | 2026-04-03T16:00:00+00:00 | Planned Maintenance will result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions. |
||
Yellow River |
Yellow River |
Other_0000000000000010905_002 | Dismissed | 2026-03-31T09:09:07+00:00 | 2026-03-31T10:00:00+00:00 | 2026-03-31T16:00:00+00:00 | Generator Compliance Test (Yellow River WFPS) is expected to commence on 31th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 10:00 to 16:00 on the 31/03/2026 |
||
Yellow River |
Yellow River |
Other_0000000000000010905_001 | Dismissed | 2026-03-30T08:48:45+00:00 | 2026-03-31T10:00:00+00:00 | 2026-03-31T16:00:00+00:00 | Generator Compliance Test (Yellow River WFPS) is expected to commence on 31th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 10:00 to 16:00 on the 31/03/2026 |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010900_001 | Active | 2026-03-27T16:50:00+00:00 | 2026-03-27T20:00:00+00:00 | 2026-03-29T19:00:00+00:00 | Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions. |
||
SSE Fiddlers Ferry Ltd |
48X0000000003966 | Other_0000000000000010781_002 | Active | 2026-03-23T16:57:24+00:00 | 2025-12-18T08:45:00+00:00 | 2027-02-28T15:00:00+00:00 | Fiddlers Ferry BESS is planned to be energised Jan 2027 under a 4 week outage and will commence commissioning Feb 2027.
Further updates will be published when firm information is available.
|
||
SSE Fiddlers Ferry Ltd |
48X0000000003966 | Other_0000000000000010781_001 | Dismissed | 2025-12-18T08:46:56+00:00 | 2025-12-18T08:45:00+00:00 | 2026-09-04T15:00:00+00:00 | Fiddlers Ferry BESS is planned to be energised October 2026 and will commence commissioning during January 2027.
Further updates will be published when firm information is available.
|
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010886_002 | Active | 2026-03-23T13:21:25+00:00 | 2026-03-20T10:45:00+00:00 | 2026-03-24T12:30:00+00:00 | Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010886_001 | Dismissed | 2026-03-20T10:39:51+00:00 | 2026-03-20T10:45:00+00:00 | 2026-03-23T12:30:00+00:00 | Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions. |
||
SSE Ferrybridge Battery Limited |
48X000000000382H | Other_0000000000000010438_007 | Active | 2026-03-20T16:08:54+00:00 | 2025-08-21T10:30:00+00:00 | 2026-03-19T13:00:00+00:00 | Ferrybridge BESS achieved commercial operations on 19th March 2026. |
||
SSE Ferrybridge Battery Limited |
48X000000000382H | Other_0000000000000010438_006 | Dismissed | 2026-03-19T13:50:47+00:00 | 2025-08-21T10:30:00+00:00 | 2026-03-19T13:00:00+00:00 | It is expected that Ferrybridge BESS will achieve commercial operations on 19th March 2026. As relevant details of the plans become firmer REMIT will be updated |
||
SSE Ferrybridge Battery Limited |
48X000000000382H | Other_0000000000000010438_005 | Dismissed | 2026-03-18T18:14:57+00:00 | 2025-08-21T10:30:00+00:00 | 2026-03-31T10:00:00+00:00 | It is expected that Ferrybridge BESS will achieve commercial operations on 19th March 2026. As relevant details of the plans become firmer REMIT will be updated |
||
SSE Ferrybridge Battery Limited |
48X000000000382H | Other_0000000000000010438_004 | Dismissed | 2026-03-10T16:18:01+00:00 | 2025-08-21T10:30:00+00:00 | 2026-03-31T10:00:00+00:00 | It is expected that Ferrybridge BESS will achieve commercial operations on 18th March 2026. As relevant details of the plans become firmer REMIT will be updated |
||
SSE Ferrybridge Battery Limited |
48X000000000382H | Other_0000000000000010438_003 | Dismissed | 2026-03-05T12:14:43+00:00 | 2025-08-21T10:30:00+00:00 | 2026-03-31T10:00:00+00:00 | It is expected that Ferrybridge BESS will achieve commercial operations on 13th March 2026. As relevant details of the plans become firmer REMIT will be updated |
||
SSE Ferrybridge Battery Limited |
48X000000000382H | Other_0000000000000010438_002 | Dismissed | 2026-02-17T16:51:31+00:00 | 2025-08-21T10:30:00+00:00 | 2026-03-31T10:00:00+00:00 | It is expected that Ferrybridge BESS will achieve commercial operations on 2nd March 2026. As relevant details of the plans become firmer REMIT will be updated |
||
SSE Ferrybridge Battery Limited |
48X000000000382H | Other_0000000000000010438_001 | Dismissed | 2025-08-21T10:21:58+00:00 | 2025-08-21T10:30:00+00:00 | 2025-12-19T10:00:00+00:00 | It is expected that Ferrybridge BESS commissioning will start in August 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 150MW being available during Q4 2025. As relevant details of the commissioning plans become firmer REMIT will be updated |
||
Hadyard Hill |
T_HADHW-1 |
Other_0000000000000010783_005 | Active | 2026-03-13T08:42:37+00:00 | 2025-12-19T09:30:00+00:00 | 2026-09-30T17:00:00+00:00 | Hadyard Hill Wind Farm remains fully unavailable following the identification of a technical fault and has been taken offline to allow a full investigation and assessment of next steps. At this stage, no reliable return-to-service date can be confirmed. This notice will be updated as soon as materially new information becomes available. |
||
Hadyard Hill |
T_HADHW-1 |
Other_0000000000000010783_004 | Dismissed | 2026-03-13T07:44:07+00:00 | 2025-12-19T09:30:00+00:00 | 2026-09-30T17:00:00+00:00 | We are currently experiencing a technical issue at Hadyard Hill Wind Farm, resulting in the site either running at a reduced output or not exporting to the grid. The issue is under investigation, and this notice will be updated as soon as further information becomes available. |
||
Hadyard Hill |
T_HADHW-1 |
Other_0000000000000010783_003 | Dismissed | 2026-03-13T07:42:14+00:00 | 2025-12-19T09:30:00+00:00 | 2026-10-30T17:00:00+00:00 | We are currently experiencing a technical issue at Hadyard Hill Wind Farm, resulting in the site either running at a reduced output or not exporting to the grid. The issue is under investigation, and this notice will be updated as soon as further information becomes available. |
||
Hadyard Hill |
T_HADHW-1 |
Other_0000000000000010783_002 | Dismissed | 2026-01-09T15:18:25+00:00 | 2025-12-19T09:30:00+00:00 | 2026-03-31T17:00:00+00:00 | We are currently experiencing a technical issue at Hadyard Hill Wind Farm, resulting in the site either running at a reduced output or not exporting to the grid. The issue is under investigation, and this notice will be updated as soon as further information becomes available. |
||
Hadyard Hill |
T_HADHW-1 |
Other_0000000000000010783_001 | Dismissed | 2025-12-19T09:56:11+00:00 | 2025-12-19T09:30:00+00:00 | 2026-01-31T17:00:00+00:00 | We are currently experiencing a technical issue at Hadyard Hill Wind Farm, resulting in the site either running at a reduced output or not exporting to the grid. The issue is under investigation, and this notice will be updated as soon as further information becomes available. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010869_002 | Active | 2026-03-09T08:31:51+00:00 | 2026-03-05T18:00:00+00:00 | 2026-03-12T12:00:00+00:00 | Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010869_001 | Dismissed | 2026-03-05T17:37:51+00:00 | 2026-03-05T18:00:00+00:00 | 2026-03-09T12:00:00+00:00 | Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions. |
||
Yellow River |
Yellow River |
Other_0000000000000010868_001 | Active | 2026-03-05T11:00:00+00:00 | 2026-03-06T11:00:00+00:00 | 2026-03-06T13:00:00+00:00 | Generator Compliance Test (Yellow River WFPS) is expected to commence on 06th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 11:00 to 13:00 on the 06/03/2026 |
||
Yellow River |
Yellow River |
Other_0000000000000010865_002 | Inactive | 2026-03-05T08:52:22+00:00 | 2026-03-05T09:00:00+00:00 | 2026-03-05T11:00:00+00:00 | Generator Compliance Test (Yellow River WFPS) is expected to commence on 05th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 09:00 to 11:00 on the 05/03/2026 |
||
Yellow River |
Yellow River |
Other_0000000000000010865_001 | Dismissed | 2026-03-04T12:59:08+00:00 | 2026-03-05T09:00:00+00:00 | 2026-03-05T11:00:00+00:00 | Generator Compliance Test (Yellow River WFPS) is expected to commence on 05th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 09:00 to 11:00 on the 05/03/2026 |
||
Yellow River |
Yellow River |
Other_0000000000000010866_002 | Inactive | 2026-03-05T08:51:59+00:00 | 2026-03-05T09:00:00+00:00 | 2026-03-05T11:00:00+00:00 | Generator Compliance Test (Yellow River WFPS) is expected to commence on 05th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 09:00 to 11:00 on the 05/03/2026 |
||
Yellow River |
Yellow River |
Other_0000000000000010866_001 | Dismissed | 2026-03-04T12:59:22+00:00 | 2026-03-05T09:00:00+00:00 | 2026-03-05T11:00:00+00:00 | Generator Compliance Test (Yellow River WFPS) is expected to commence on 05th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 09:00 to 11:00 on the 05/03/2026 |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010847_003 | Active | 2026-02-21T12:00:12+00:00 | 2026-02-19T16:30:00+00:00 | 2026-02-21T12:00:00+00:00 | Due to low reservoir levels at the Sloy scheme, there is an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4. Availability will continue to be dependent on inflow conditions and will be declared through MEL submissions. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010847_002 | Dismissed | 2026-02-20T09:10:21+00:00 | 2026-02-19T16:30:00+00:00 | 2026-02-21T23:00:00+00:00 | Due to low reservoir levels at the Sloy scheme, there is an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4. Availability will continue to be dependent on inflow conditions and will be declared through MEL submissions. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010847_001 | Dismissed | 2026-02-19T16:28:00+00:00 | 2026-02-19T16:30:00+00:00 | 2026-02-20T12:00:00+00:00 | Due to low reservoir levels at the Sloy scheme, there is an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4. Availability will continue to be dependent on inflow conditions and will be declared through MEL submissions. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010850_002 | Dismissed | 2026-02-20T14:27:21+00:00 | 2026-02-20T14:15:00+00:00 | 2026-09-30T14:20:00+00:00 | This is a Test Message for Cloiche Wind Farm. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010850_001 | Dismissed | 2026-02-20T14:15:07+00:00 | 2026-02-20T14:15:00+00:00 | 2026-09-30T14:20:00+00:00 | This is a Test Message for Cloiche Wind Farm. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010840_001 | Active | 2026-02-09T10:55:18+00:00 | 2026-02-10T08:00:00+00:00 | 2026-02-10T12:30:00+00:00 | Routine Testing will result in an aggregate unavailability of 152.5MW across BMU's M_SLOY1, T_SLOY2, T_SLOY3, M_SLOY4 |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010835_002 | Active | 2026-02-02T16:26:59+00:00 | 2026-01-30T16:30:00+00:00 | 2026-02-05T12:00:00+00:00 | Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000010835_001 | Dismissed | 2026-01-30T16:27:00+00:00 | 2026-01-30T16:30:00+00:00 | 2026-02-03T08:00:00+00:00 | Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions. |
||
Yellow River |
Yellow River |
Other_0000000000000010794_002 | Inactive | 2026-01-29T07:18:53+00:00 | 2026-01-29T10:00:00+00:00 | 2026-01-29T16:00:00+00:00 | Generator Testing - Yellow River WFPS: Reactive Power Capability expected to commence on 29 January. During the test, site output may vary between 0 MW and full resource availability. |
||
Yellow River |
Yellow River |
Other_0000000000000010794_001 | Dismissed | 2026-01-06T16:49:53+00:00 | 2026-01-29T10:00:00+00:00 | 2026-01-29T16:00:00+00:00 | Generator Testing - Yellow River WFPS: Reactive Power Capability expected to commence on 29 January. During the test, site output may vary between 0 MW and full resource availability. |
||
Yellow River |
Yellow River |
Other_0000000000000010821_002 | Active | 2026-01-27T13:14:15+00:00 | 2026-01-27T10:00:00+00:00 | 2026-01-27T13:14:00+00:00 | Generator Compliance Test (Yellow River WFPS) is expected to commence on 27th of January 2026. During the test, site output may vary between 0–101 MW |
||
Yellow River |
Yellow River |
Other_0000000000000010821_001 | Dismissed | 2026-01-26T10:03:08+00:00 | 2026-01-27T10:00:00+00:00 | 2026-01-27T16:00:00+00:00 | Generator Compliance Test (Yellow River WFPS) is expected to commence on 27th of January 2026. During the test, site output may vary between 0–101 MW |
||
Glendoe |
T_GLNDO-1 |
Other_0000000000000010818_001 | Active | 2026-01-23T16:36:17+00:00 | 2026-01-26T16:00:00+00:00 | 2026-01-26T20:00:00+00:00 | There is generation testing required at Glendoe (GLNDO-1)on 26th January 16:00 - 20:00. |
||
SSE Battery Monk Fryston Limited |
48X0000000004020 | Other_0000000000000010817_002 | Dismissed | 2026-01-22T17:44:06+00:00 | 2026-01-22T17:39:00+00:00 | 2026-01-22T17:45:00+00:00 | Test Message for Monk Fryston Market Participant level |
||
SSE Battery Monk Fryston Limited |
48X0000000004020 | Other_0000000000000010817_001 | Dismissed | 2026-01-22T17:40:39+00:00 | 2026-01-22T17:39:00+00:00 | 2026-01-22T17:45:00+00:00 | Test Message for Monk Fryston Market Participant level |
||
SSE Battery Monk Fryston Limited |
48X0000000004020 | Other_0000000000000010814_002 | Dismissed | 2026-01-22T17:39:31+00:00 | 2026-01-22T17:20:00+00:00 | 2026-01-22T17:25:00+00:00 | Test message for Monk Fryston |
||
SSE Battery Monk Fryston Limited |
48X0000000004020 | Other_0000000000000010814_001 | Dismissed | 2026-01-22T17:18:04+00:00 | 2026-01-22T17:20:00+00:00 | 2026-01-22T17:25:00+00:00 | Test message for Monk Fryston |
||
Monk Fryston |
T_MKFRB-1 |
Other_0000000000000010816_002 | Dismissed | 2026-01-22T17:39:24+00:00 | 2026-01-22T17:26:00+00:00 | 2026-01-22T17:30:00+00:00 | Test Messagefor Monk Fryston as BM |
||
Monk Fryston |
T_MKFRB-1 |
Other_0000000000000010816_001 | Dismissed | 2026-01-22T17:27:40+00:00 | 2026-01-22T17:26:00+00:00 | 2026-01-22T17:30:00+00:00 | Test Messagefor Monk Fryston as BM |
||