SSE Thermal Generation and Gas Storage REMIT information is no longer being updated on this page.
For SSE Thermal Generation and Gas Storage REMIT Information (Unavailability of Facilities and Other Market Information), please visit SSE Thermal REMIT.

Last update at: 2026-04-23T19:00:00+00:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
1 2 3 4 5 >
SSE Battery Monk Fryston Limited
48X0000000004020
Other_0000000000000010935_002 Active 2026-04-23T18:41:21+00:00 2026-04-23T14:30:00+00:00 2027-01-29T17:00:00+00:00
Monk Fryston 400/275kV BESS (320 MW) is currently planned to be initially energised in July 2026 under a restricted Initial Operational Notification (ION) limited to 20%. The Commercial Operation Date (COD) is proposed for early 2027. This information will be updated as further details become available.
SSE Battery Monk Fryston Limited
48X0000000004020
Other_0000000000000010935_001 Dismissed 2026-04-23T13:56:20+00:00 2026-04-23T14:30:00+00:00 2027-01-29T17:00:00+00:00
Monk Fryston 400/275kV BESS (300 MW) is currently planned to be initially energised in July 2026 under a restricted Initial Operational Notification (ION) limited to 20%. The Commercial Operation Date (COD) is proposed for early 2027. This information will be updated as further details become available.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000010933_001 Active 2026-04-19T19:54:04+00:00 2026-04-19T20:50:00+00:00 2026-12-31T23:00:00+00:00
Dogger Bank A is currently in commissioning. Current available capacity will be specified at all times in the individual BMU notices. Available capacity is expected to rise broadly linearly, with output inherently varying with fluctuations during the commissioning phase, with the total capacity of 1.2GW being substantially all available by end Q4 2026. Ongoing REMIT notices for each BMU will provide near-term available capacity and will be kept updated throughout the commissioning period.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000010415_004 Dismissed 2026-04-19T19:52:02+00:00 2025-08-08T11:05:15+00:00 2026-07-01T16:00:00+00:00
Dogger Bank A is currently in the commissioning phase, with 90 out of 95 turbines installed as at 30 November 2025. Installation is expected to complete by the end of December 2025. As at 30 November 2025 approximately 700MW was available and a steady increase is forecast, with the total capacity of 1.2GW being substantially available for generation by the end of Q2 2026. As commissioning progresses the available capacity will continue to be updated within the notices of unavailability on REMIT.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000010415_003 Dismissed 2025-12-11T08:52:00+00:00 2025-08-08T11:05:15+00:00 2026-07-01T16:00:00+00:00
Dogger Bank A is currently in the commissioning phase, with 90 out of 95 turbines installed as at 30 November 2025. Installation is expected to complete by the end of December 2025. As at 30 November 2025 approximately 700MW was available and a steady increase is forecast, with the total capacity of 1.2GW being substantially available for generation by the end of Q2 2026. As commissioning progresses the available capacity will continue to be updated within the notices of unavailability on REMIT.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000010415_002 Dismissed 2025-08-29T13:29:23+00:00 2025-08-08T11:05:15+00:00 2025-12-31T16:00:00+00:00
• Dogger Bank A is currently in the commissioning phase, with 832MW of installed capacity as at 31 July 2025. It is expected that there will be a steady increase in installed capacity with installation expected to complete by the end of 2025 and the total capacity of 1.2 GW being substantially all available by the end of Q4 2025.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000010415_001 Dismissed 2025-08-08T10:54:41+00:00 2025-08-08T11:05:15+00:00 2025-08-29T16:00:25+00:00
Dogger Bank A is currently in the commissioning phase, with 832MW of installed capacity as at 31 July 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available during Q4 2025, subject to stabilisation of turbine performance. As relevant details of the commissioning plans become firmer this notice will be updated
SSE GENERATION
48X000000000077M
Other_0000000000000010910_002 Active 2026-04-02T15:29:54+00:00 2026-04-01T17:15:00+00:00 2026-04-06T13:00:00+00:00
Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions.
SSE GENERATION
48X000000000077M
Other_0000000000000010910_001 Dismissed 2026-04-01T16:14:13+00:00 2026-04-01T17:15:00+00:00 2026-04-03T17:00:00+00:00
Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions.
SSE GENERATION
48X000000000077M
Other_0000000000000010897_003 Dismissed 2026-04-01T16:12:16+00:00 2026-04-01T08:00:00+00:00 2026-04-01T17:15:00+00:00
Planned Maintenance will result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions.
SSE GENERATION
48X000000000077M
Other_0000000000000010897_002 Dismissed 2026-04-01T09:44:35+00:00 2026-04-01T08:00:00+00:00 2026-04-02T16:00:00+00:00
Planned Maintenance will result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions.
SSE GENERATION
48X000000000077M
Other_0000000000000010897_001 Dismissed 2026-03-26T11:09:42+00:00 2026-04-01T08:00:00+00:00 2026-04-03T16:00:00+00:00
Planned Maintenance will result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions.
Yellow River
Yellow River
Other_0000000000000010905_002 Dismissed 2026-03-31T09:09:07+00:00 2026-03-31T10:00:00+00:00 2026-03-31T16:00:00+00:00
Generator Compliance Test (Yellow River WFPS) is expected to commence on 31th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 10:00 to 16:00 on the 31/03/2026
Yellow River
Yellow River
Other_0000000000000010905_001 Dismissed 2026-03-30T08:48:45+00:00 2026-03-31T10:00:00+00:00 2026-03-31T16:00:00+00:00
Generator Compliance Test (Yellow River WFPS) is expected to commence on 31th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 10:00 to 16:00 on the 31/03/2026
SSE GENERATION
48X000000000077M
Other_0000000000000010900_001 Active 2026-03-27T16:50:00+00:00 2026-03-27T20:00:00+00:00 2026-03-29T19:00:00+00:00
Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions.
SSE Fiddlers Ferry Ltd
48X0000000003966
Other_0000000000000010781_002 Active 2026-03-23T16:57:24+00:00 2025-12-18T08:45:00+00:00 2027-02-28T15:00:00+00:00
Fiddlers Ferry BESS is planned to be energised Jan 2027 under a 4 week outage and will commence commissioning Feb 2027. Further updates will be published when firm information is available.
SSE Fiddlers Ferry Ltd
48X0000000003966
Other_0000000000000010781_001 Dismissed 2025-12-18T08:46:56+00:00 2025-12-18T08:45:00+00:00 2026-09-04T15:00:00+00:00
Fiddlers Ferry BESS is planned to be energised October 2026 and will commence commissioning during January 2027. Further updates will be published when firm information is available.
SSE GENERATION
48X000000000077M
Other_0000000000000010886_002 Active 2026-03-23T13:21:25+00:00 2026-03-20T10:45:00+00:00 2026-03-24T12:30:00+00:00
Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions.
SSE GENERATION
48X000000000077M
Other_0000000000000010886_001 Dismissed 2026-03-20T10:39:51+00:00 2026-03-20T10:45:00+00:00 2026-03-23T12:30:00+00:00
Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions.
SSE Ferrybridge Battery Limited
48X000000000382H
Other_0000000000000010438_007 Active 2026-03-20T16:08:54+00:00 2025-08-21T10:30:00+00:00 2026-03-19T13:00:00+00:00
Ferrybridge BESS achieved commercial operations on 19th March 2026.
SSE Ferrybridge Battery Limited
48X000000000382H
Other_0000000000000010438_006 Dismissed 2026-03-19T13:50:47+00:00 2025-08-21T10:30:00+00:00 2026-03-19T13:00:00+00:00
It is expected that Ferrybridge BESS will achieve commercial operations on 19th March 2026. As relevant details of the plans become firmer REMIT will be updated
SSE Ferrybridge Battery Limited
48X000000000382H
Other_0000000000000010438_005 Dismissed 2026-03-18T18:14:57+00:00 2025-08-21T10:30:00+00:00 2026-03-31T10:00:00+00:00
It is expected that Ferrybridge BESS will achieve commercial operations on 19th March 2026. As relevant details of the plans become firmer REMIT will be updated
SSE Ferrybridge Battery Limited
48X000000000382H
Other_0000000000000010438_004 Dismissed 2026-03-10T16:18:01+00:00 2025-08-21T10:30:00+00:00 2026-03-31T10:00:00+00:00
It is expected that Ferrybridge BESS will achieve commercial operations on 18th March 2026. As relevant details of the plans become firmer REMIT will be updated
SSE Ferrybridge Battery Limited
48X000000000382H
Other_0000000000000010438_003 Dismissed 2026-03-05T12:14:43+00:00 2025-08-21T10:30:00+00:00 2026-03-31T10:00:00+00:00
It is expected that Ferrybridge BESS will achieve commercial operations on 13th March 2026. As relevant details of the plans become firmer REMIT will be updated
SSE Ferrybridge Battery Limited
48X000000000382H
Other_0000000000000010438_002 Dismissed 2026-02-17T16:51:31+00:00 2025-08-21T10:30:00+00:00 2026-03-31T10:00:00+00:00
It is expected that Ferrybridge BESS will achieve commercial operations on 2nd March 2026. As relevant details of the plans become firmer REMIT will be updated
SSE Ferrybridge Battery Limited
48X000000000382H
Other_0000000000000010438_001 Dismissed 2025-08-21T10:21:58+00:00 2025-08-21T10:30:00+00:00 2025-12-19T10:00:00+00:00
It is expected that Ferrybridge BESS commissioning will start in August 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 150MW being available during Q4 2025. As relevant details of the commissioning plans become firmer REMIT will be updated
Hadyard Hill
T_HADHW-1
Other_0000000000000010783_005 Active 2026-03-13T08:42:37+00:00 2025-12-19T09:30:00+00:00 2026-09-30T17:00:00+00:00
Hadyard Hill Wind Farm remains fully unavailable following the identification of a technical fault and has been taken offline to allow a full investigation and assessment of next steps. At this stage, no reliable return-to-service date can be confirmed. This notice will be updated as soon as materially new information becomes available.
Hadyard Hill
T_HADHW-1
Other_0000000000000010783_004 Dismissed 2026-03-13T07:44:07+00:00 2025-12-19T09:30:00+00:00 2026-09-30T17:00:00+00:00
We are currently experiencing a technical issue at Hadyard Hill Wind Farm, resulting in the site either running at a reduced output or not exporting to the grid. The issue is under investigation, and this notice will be updated as soon as further information becomes available.
Hadyard Hill
T_HADHW-1
Other_0000000000000010783_003 Dismissed 2026-03-13T07:42:14+00:00 2025-12-19T09:30:00+00:00 2026-10-30T17:00:00+00:00
We are currently experiencing a technical issue at Hadyard Hill Wind Farm, resulting in the site either running at a reduced output or not exporting to the grid. The issue is under investigation, and this notice will be updated as soon as further information becomes available.
Hadyard Hill
T_HADHW-1
Other_0000000000000010783_002 Dismissed 2026-01-09T15:18:25+00:00 2025-12-19T09:30:00+00:00 2026-03-31T17:00:00+00:00
We are currently experiencing a technical issue at Hadyard Hill Wind Farm, resulting in the site either running at a reduced output or not exporting to the grid. The issue is under investigation, and this notice will be updated as soon as further information becomes available.
Hadyard Hill
T_HADHW-1
Other_0000000000000010783_001 Dismissed 2025-12-19T09:56:11+00:00 2025-12-19T09:30:00+00:00 2026-01-31T17:00:00+00:00
We are currently experiencing a technical issue at Hadyard Hill Wind Farm, resulting in the site either running at a reduced output or not exporting to the grid. The issue is under investigation, and this notice will be updated as soon as further information becomes available.
SSE GENERATION
48X000000000077M
Other_0000000000000010869_002 Active 2026-03-09T08:31:51+00:00 2026-03-05T18:00:00+00:00 2026-03-12T12:00:00+00:00
Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions.
SSE GENERATION
48X000000000077M
Other_0000000000000010869_001 Dismissed 2026-03-05T17:37:51+00:00 2026-03-05T18:00:00+00:00 2026-03-09T12:00:00+00:00
Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions.
Yellow River
Yellow River
Other_0000000000000010868_001 Active 2026-03-05T11:00:00+00:00 2026-03-06T11:00:00+00:00 2026-03-06T13:00:00+00:00
Generator Compliance Test (Yellow River WFPS) is expected to commence on 06th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 11:00 to 13:00 on the 06/03/2026
Yellow River
Yellow River
Other_0000000000000010865_002 Inactive 2026-03-05T08:52:22+00:00 2026-03-05T09:00:00+00:00 2026-03-05T11:00:00+00:00
Generator Compliance Test (Yellow River WFPS) is expected to commence on 05th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 09:00 to 11:00 on the 05/03/2026
Yellow River
Yellow River
Other_0000000000000010865_001 Dismissed 2026-03-04T12:59:08+00:00 2026-03-05T09:00:00+00:00 2026-03-05T11:00:00+00:00
Generator Compliance Test (Yellow River WFPS) is expected to commence on 05th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 09:00 to 11:00 on the 05/03/2026
Yellow River
Yellow River
Other_0000000000000010866_002 Inactive 2026-03-05T08:51:59+00:00 2026-03-05T09:00:00+00:00 2026-03-05T11:00:00+00:00
Generator Compliance Test (Yellow River WFPS) is expected to commence on 05th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 09:00 to 11:00 on the 05/03/2026
Yellow River
Yellow River
Other_0000000000000010866_001 Dismissed 2026-03-04T12:59:22+00:00 2026-03-05T09:00:00+00:00 2026-03-05T11:00:00+00:00
Generator Compliance Test (Yellow River WFPS) is expected to commence on 05th of March 2026. During the test, site output may vary between 0–101 MW." Notice to be from 09:00 to 11:00 on the 05/03/2026
SSE GENERATION
48X000000000077M
Other_0000000000000010847_003 Active 2026-02-21T12:00:12+00:00 2026-02-19T16:30:00+00:00 2026-02-21T12:00:00+00:00
Due to low reservoir levels at the Sloy scheme, there is an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4. Availability will continue to be dependent on inflow conditions and will be declared through MEL submissions.
SSE GENERATION
48X000000000077M
Other_0000000000000010847_002 Dismissed 2026-02-20T09:10:21+00:00 2026-02-19T16:30:00+00:00 2026-02-21T23:00:00+00:00
Due to low reservoir levels at the Sloy scheme, there is an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4. Availability will continue to be dependent on inflow conditions and will be declared through MEL submissions.
SSE GENERATION
48X000000000077M
Other_0000000000000010847_001 Dismissed 2026-02-19T16:28:00+00:00 2026-02-19T16:30:00+00:00 2026-02-20T12:00:00+00:00
Due to low reservoir levels at the Sloy scheme, there is an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4. Availability will continue to be dependent on inflow conditions and will be declared through MEL submissions.
SSE GENERATION
48X000000000077M
Other_0000000000000010850_002 Dismissed 2026-02-20T14:27:21+00:00 2026-02-20T14:15:00+00:00 2026-09-30T14:20:00+00:00
This is a Test Message for Cloiche Wind Farm.
SSE GENERATION
48X000000000077M
Other_0000000000000010850_001 Dismissed 2026-02-20T14:15:07+00:00 2026-02-20T14:15:00+00:00 2026-09-30T14:20:00+00:00
This is a Test Message for Cloiche Wind Farm.
SSE GENERATION
48X000000000077M
Other_0000000000000010840_001 Active 2026-02-09T10:55:18+00:00 2026-02-10T08:00:00+00:00 2026-02-10T12:30:00+00:00
Routine Testing will result in an aggregate unavailability of 152.5MW across BMU's M_SLOY1, T_SLOY2, T_SLOY3, M_SLOY4
SSE GENERATION
48X000000000077M
Other_0000000000000010835_002 Active 2026-02-02T16:26:59+00:00 2026-01-30T16:30:00+00:00 2026-02-05T12:00:00+00:00
Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions.
SSE GENERATION
48X000000000077M
Other_0000000000000010835_001 Dismissed 2026-01-30T16:27:00+00:00 2026-01-30T16:30:00+00:00 2026-02-03T08:00:00+00:00
Due to low reservoir levels at the Sloy scheme, current forecasts indicate that, if conditions continue, remaining available water may be fully utilised pending further inflow. This is expected to result in an aggregate unavailability of 152.5 MW across BMUs M_SLOY 1, T_SLOY 2, T_SLOY 3 and M_SLOY 4, which will be confirmed by MEL submissions.
Yellow River
Yellow River
Other_0000000000000010794_002 Inactive 2026-01-29T07:18:53+00:00 2026-01-29T10:00:00+00:00 2026-01-29T16:00:00+00:00
Generator Testing - Yellow River WFPS: Reactive Power Capability expected to commence on 29 January. During the test, site output may vary between 0 MW and full resource availability.
Yellow River
Yellow River
Other_0000000000000010794_001 Dismissed 2026-01-06T16:49:53+00:00 2026-01-29T10:00:00+00:00 2026-01-29T16:00:00+00:00
Generator Testing - Yellow River WFPS: Reactive Power Capability expected to commence on 29 January. During the test, site output may vary between 0 MW and full resource availability.
Yellow River
Yellow River
Other_0000000000000010821_002 Active 2026-01-27T13:14:15+00:00 2026-01-27T10:00:00+00:00 2026-01-27T13:14:00+00:00
Generator Compliance Test (Yellow River WFPS) is expected to commence on 27th of January 2026. During the test, site output may vary between 0–101 MW
Yellow River
Yellow River
Other_0000000000000010821_001 Dismissed 2026-01-26T10:03:08+00:00 2026-01-27T10:00:00+00:00 2026-01-27T16:00:00+00:00
Generator Compliance Test (Yellow River WFPS) is expected to commence on 27th of January 2026. During the test, site output may vary between 0–101 MW