This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2024-04-25T12:30:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
1 2 3 4 5 >
Peterhead
T_PEHE-1
Other_0000000000000009046_001 Active 2024-04-25T12:04:26+01:00 2024-04-27T23:00:00+01:00 2024-05-21T23:00:00+01:00
T_PEHE-1. Auxiliary boiler taken out of service to allow statutory inspection to be completed. While auxiliary boiler is out of service, block in inflexible following shutdown as a period of 37 hours is required to allow sufficient cooling of steam turbine to allow re-start without auxiliary steam.
Keadby
T_KEAD-1
Other_0000000000000009044_004 Active 2024-04-25T10:49:47+01:00 2024-04-26T00:00:00+01:00 2024-04-26T23:59:59+01:00
Asset Integrity. Following the KEAD_1 out-of-merit run commencing 26th April ’24, a dynamic data change to 720min NDZ will be implemented.
Keadby
T_KEAD-1
Other_0000000000000009044_003 Dismissed 2024-04-25T10:23:07+01:00 2024-04-26T00:00:00+01:00 2024-04-26T23:59:59+01:00
Asset Integrity. Following the KEAD_1 out-of-merit run commencing 25th April ’24, a dynamic data change to 720min NDZ will be implemented.
Keadby
T_KEAD-1
Other_0000000000000009044_002 Dismissed 2024-04-25T09:44:41+01:00 2024-04-26T00:00:00+01:00 2024-06-06T00:00:00+01:00
KEAD_1 10 hour on load run requested for preservation of plant during Friday 26th April 2024.
Keadby
T_KEAD-1
Other_0000000000000009044_001 Dismissed 2024-04-24T19:54:16+01:00 2024-04-25T00:00:00+01:00 2024-06-06T00:00:00+01:00
Following the KEAD_1 out-of-merit run commencing 25th April ’24, a dynamic data change to 720min NDZ will be implemented.
Other_0000000000000008908_004 Inactive 2024-03-18T01:02:32+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 4-5 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_003 Dismissed 2024-03-08T11:26:43+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 4-5 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_002 Dismissed 2024-03-05T14:03:34+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 2-3 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_001 Dismissed 2024-03-04T13:13:31+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified.
Other_0000000000000008899_004 Inactive 2024-03-08T01:02:31+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Medway
T_MEDP-1
Other_0000000000000008899_003 Dismissed 2024-03-05T14:59:17+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Medway
T_MEDP-1
Other_0000000000000008899_002 Dismissed 2024-02-29T14:00:58+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Medway
T_MEDP-1
Other_0000000000000008899_001 Dismissed 2024-02-29T13:41:02+00:00 2024-03-04T06:00:00+00:00 2024-04-04T23:59:00+01:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Great Island
Great Island
Other_0000000000000008845_002 Inactive 2024-02-13T14:47:42+00:00 2030-02-13T14:40:00+00:00 2030-02-13T14:41:00+00:00
This is a test of SSE REMIT application functionality only. No action should be taken.
Great Island
Great Island
Other_0000000000000008845_001 Dismissed 2024-02-13T14:42:10+00:00 2030-02-13T14:40:00+00:00 2030-02-13T14:41:00+00:00
This is a test of SSE REMIT application functionality only. No action should be taken.
Great Island
Great Island
Other_0000000000000008475_002 Active 2023-10-02T17:20:09+01:00 2023-10-02T17:05:00+01:00 2024-05-17T22:00:00+01:00
Great Island is available for running on secondary fuel in the event of a gas system emergency
Great Island
Great Island
Other_0000000000000008475_001 Dismissed 2023-10-02T17:06:20+01:00 2023-10-02T17:05:00+01:00
Great Island is available for running on secondary fuel in the event of a gas system emergency
Great Island
Great Island
Other_0000000000000008203_004 Dismissed 2023-10-02T17:07:15+01:00 2023-06-19T10:07:00+01:00 2024-05-17T22:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Great Island
Great Island
Other_0000000000000008203_003 Dismissed 2023-07-27T12:34:51+01:00 2023-06-19T10:07:00+01:00 2024-05-17T22:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Great Island
Great Island
Other_0000000000000008203_002 Dismissed 2023-06-19T10:34:59+01:00 2023-06-19T10:07:00+01:00 2023-07-28T10:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Great Island
Great Island
Other_0000000000000008203_001 Dismissed 2023-06-19T10:13:07+01:00 2023-06-19T10:07:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Peterhead
T_PEHE-1
Other_0000000000000008437_006 Dismissed 2023-09-22T15:13:14+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested
Peterhead
T_PEHE-1
Other_0000000000000008437_005 Dismissed 2023-09-21T17:33:37+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested
Peterhead
T_PEHE-1
Other_0000000000000008437_004 Dismissed 2023-09-21T17:03:58+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:01:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times in Elexon
Peterhead
T_PEHE-1
Other_0000000000000008437_003 Dismissed 2023-09-21T16:48:56+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:01:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008437_002 Dismissed 2023-09-21T14:26:32+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
T_PEHE-1 Running at Circa 550MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008437_001 Dismissed 2023-09-20T08:32:32+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
Running at Circa 550MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008436_003 Dismissed 2023-09-21T14:38:30+01:00 2023-09-21T12:00:00+01:00 2023-09-21T19:00:00+01:00
T_PEHE-1 Running at Circa 300MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008436_002 Dismissed 2023-09-21T14:27:09+01:00 2023-09-21T12:00:00+01:00 2023-09-21T19:00:00+01:00
T_PEHE-1 Running at Circa 300MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008436_001 Dismissed 2023-09-20T08:29:55+01:00 2023-09-21T12:00:00+01:00 2023-09-21T19:00:00+01:00
Running at Circa 300MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008420_002 Dismissed 2023-09-18T12:19:36+01:00 2023-09-19T10:00:00+01:00 2023-09-19T19:00:00+01:00
Operating at circa 300MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008420_001 Dismissed 2023-09-15T15:01:11+01:00 2023-09-19T10:00:00+01:00 2023-09-19T19:00:00+01:00
Operating at circa 300MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008421_002 Dismissed 2023-09-18T12:19:17+01:00 2023-09-20T08:00:00+01:00 2023-09-20T19:00:00+01:00
Operating at circa 550MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008421_001 Dismissed 2023-09-15T15:02:40+01:00 2023-09-20T08:00:00+01:00 2023-09-20T19:00:00+01:00
Operating at circa 550MW for statutory testing.
Other_0000000000000007814_002 Inactive 2023-07-06T01:02:32+01:00 2022-12-22T17:39:00+00:00 2023-07-06T00:00:00+01:00
Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023
Medway
T_MEDP-1
Other_0000000000000007814_001 Dismissed 2022-12-22T17:45:01+00:00 2022-12-22T17:39:00+00:00 2023-07-06T00:00:00+01:00
Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023
Tawnaghmore
TAWN1
Other_0000000000000008024_002 Inactive 2023-03-16T09:40:56+00:00 2027-03-16T09:39:00+00:00 2027-03-16T09:40:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Tawnaghmore
TAWN1
Other_0000000000000008024_001 Dismissed 2023-03-16T09:40:16+00:00 2027-03-16T09:39:00+00:00 2027-03-16T09:40:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Rhode
RHODE1
Other_0000000000000008023_002 Inactive 2023-03-16T09:39:01+00:00 2027-03-16T09:37:00+00:00 2027-03-16T09:38:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Rhode
RHODE1
Other_0000000000000008023_001 Dismissed 2023-03-16T09:38:18+00:00 2027-03-16T09:37:00+00:00 2027-03-16T09:38:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Tarbert
TB3
Other_0000000000000008022_002 Inactive 2023-03-16T09:36:20+00:00 2027-03-16T09:33:00+00:00 2027-03-16T09:34:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Tarbert
TB3
Other_0000000000000008022_001 Dismissed 2023-03-16T09:34:37+00:00 2027-03-16T09:33:00+00:00 2027-03-16T09:34:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Great Island
Great Island
Other_0000000000000008021_002 Inactive 2023-03-15T13:51:41+00:00 2027-03-15T13:47:00+00:00 2027-03-15T13:48:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Great Island
Great Island
Other_0000000000000008021_001 Dismissed 2023-03-15T13:49:55+00:00 2027-03-15T13:47:00+00:00 2027-03-15T13:48:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Great Island
Great Island
Other_0000000000000008020_002 Inactive 2023-03-15T12:11:38+00:00 2027-03-15T11:45:00+00:00 2027-03-15T11:46:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Great Island
Great Island
Other_0000000000000008020_001 Dismissed 2023-03-15T11:40:21+00:00 2027-03-15T11:45:00+00:00 2027-03-15T11:46:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Keadby
T_KEAD-1
Other_0000000000000007785_001 Dismissed 2022-12-19T13:59:31+00:00 2025-03-01T13:53:00+00:00 2025-03-01T13:55:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
Keadby
T_KEAD-1
Other_0000000000000007785_001 Dismissed 2022-12-21T11:51:47+00:00 2025-03-01T13:53:00+00:00 2025-03-01T13:55:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
Keadby
T_KEAD-1
Other_0000000000000007760_001 Dismissed 2022-12-05T14:58:16+00:00 2026-12-06T00:00:00+00:00 2026-12-06T00:01:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
Keadby
T_KEAD-1
Other_0000000000000007760_001 Dismissed 2022-12-05T14:44:18+00:00 2026-12-05T00:00:00+00:00 2026-12-05T00:01:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.