Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 1 2 3 4 5 > | ||||||||||||||||||
T_GRGBW-1 | 48W00000GRGBW-1V | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000007954_001 | Dismissed | Planned | Production unavailability | 2023-02-15T13:40:51+00:00 | 2023-02-15T13:40:00+00:00 | 2023-02-15T14:00:00+00:00 | MW | 10 | 155 | 165 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_GRGBW-1 | 48W00000GRGBW-1V | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000007854_002 | Dismissed | Planned | Production unavailability | 2023-01-18T14:06:50+00:00 | 2023-01-18T13:30:00+00:00 | 2023-01-18T14:00:00+00:00 | MW | 10 | 155 | 165 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_GRGBW-1 | 48W00000GRGBW-1V | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000007854_001 | Dismissed | Planned | Production unavailability | 2023-01-18T13:25:48+00:00 | 2023-01-18T13:30:00+00:00 | 2023-01-18T14:00:00+00:00 | MW | 10 | 155 | 165 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009028_002 | Dismissed | Planned | Production unavailability | 2024-04-17T16:54:52+01:00 | 2024-04-17T16:45:00+01:00 | 2024-04-17T16:50:00+01:00 | MW | 0 | 9 | 9 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009028_001 | Dismissed | Planned | Production unavailability | 2024-04-17T16:43:16+01:00 | 2024-04-17T16:45:00+01:00 | 2024-04-17T16:50:00+01:00 | MW | 9 | 0 | 9 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009021_003 | Dismissed | Planned | Production unavailability | 2024-04-16T14:05:58+01:00 | 2024-04-16T13:00:00+01:00 | 2024-04-16T14:00:00+01:00 | MW | 0 | 10 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009021_002 | Dismissed | Planned | Production unavailability | 2024-04-16T13:33:19+01:00 | 2024-04-16T13:00:00+01:00 | 2024-04-16T14:00:00+01:00 | MW | 10 | 0 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009021_001 | Dismissed | Planned | Production unavailability | 2024-04-16T13:00:49+01:00 | 2024-04-16T13:00:00+01:00 | 2024-04-16T13:30:00+01:00 | MW | 10 | 0 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008955_003 | Dismissed | Planned | Production unavailability | 2024-03-22T11:46:50+00:00 | 2024-03-22T10:30:00+00:00 | 2024-03-22T11:30:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008955_002 | Dismissed | Planned | Production unavailability | 2024-03-22T11:10:29+00:00 | 2024-03-22T10:30:00+00:00 | 2024-03-22T11:30:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008955_001 | Dismissed | Planned | Production unavailability | 2024-03-22T10:24:43+00:00 | 2024-03-22T10:30:00+00:00 | 2024-03-22T11:00:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008915_002 | Dismissed | Planned | Production unavailability | 2024-03-06T17:00:02+00:00 | 2024-03-06T16:30:00+00:00 | 2024-03-06T17:00:00+00:00 | MW | 10 | 0 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008915_001 | Dismissed | Planned | Production unavailability | 2024-03-06T16:27:55+00:00 | 2024-03-06T16:30:00+00:00 | 2024-03-06T17:00:00+00:00 | MW | 10 | 0 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008880_003 | Dismissed | Planned | Production unavailability | 2024-02-26T15:27:37+00:00 | 2024-02-26T09:40:00+00:00 | 2024-02-26T15:00:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008880_002 | Dismissed | Planned | Production unavailability | 2024-02-26T10:19:17+00:00 | 2024-02-26T09:40:00+00:00 | 2024-02-26T15:00:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008880_001 | Dismissed | Planned | Production unavailability | 2024-02-26T09:38:02+00:00 | 2024-02-26T09:40:00+00:00 | 2024-02-26T10:00:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008852_002 | Dismissed | Planned | Production unavailability | 2024-02-15T16:30:32+00:00 | 2024-02-15T15:31:00+00:00 | 2024-02-15T15:51:00+00:00 | MW | 10 | 0 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008852_001 | Dismissed | Planned | Production unavailability | 2024-02-15T15:32:03+00:00 | 2024-02-15T15:31:00+00:00 | 2024-02-15T15:51:00+00:00 | MW | 10 | 0 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008851_002 | Dismissed | Planned | Production unavailability | 2024-02-15T15:39:56+00:00 | 2024-02-15T15:10:00+00:00 | 2024-02-15T15:30:00+00:00 | MW | 0 | 0 | 0 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008851_001 | Dismissed | Planned | Production unavailability | 2024-02-15T15:10:53+00:00 | 2024-02-15T15:10:00+00:00 | 2024-02-15T15:30:00+00:00 | MW | 0 | 0 | 0 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009043_002 | Active | Planned | Production unavailability | 2024-04-25T08:28:36+01:00 | 2024-04-23T09:00:00+01:00 | 2024-04-29T10:00:00+01:00 | MW | 103 | 54 | 157 | Shutdown | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009043_001 | Dismissed | Planned | Production unavailability | 2024-04-23T10:11:51+01:00 | 2024-04-23T09:00:00+01:00 | 2024-04-26T10:11:00+01:00 | MW | 103 | 54 | 157 | Shutdown | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008961_006 | Inactive | Planned | Production unavailability | 2024-04-23T10:02:31+01:00 | 2024-04-11T08:30:00+01:00 | 2024-04-23T09:00:00+01:00 | MW | 105 | 52 | 157 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008961_005 | Dismissed | Planned | Production unavailability | 2024-04-19T13:09:27+01:00 | 2024-04-11T08:30:00+01:00 | 2024-04-23T09:00:00+01:00 | MW | 105 | 52 | 157 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008961_004 | Dismissed | Planned | Production unavailability | 2024-04-19T13:08:40+01:00 | 2024-04-11T08:30:00+01:00 | 2024-04-23T09:00:00+01:00 | MW | 157 | 0 | 157 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008961_003 | Dismissed | Planned | Production unavailability | 2024-04-18T09:44:35+01:00 | 2024-04-11T08:30:00+01:00 | 2024-04-23T09:00:00+01:00 | MW | 250 | 52 | 302 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008961_002 | Dismissed | Planned | Production unavailability | 2024-04-11T08:37:44+01:00 | 2024-04-11T08:30:00+01:00 | 2024-04-19T09:00:00+01:00 | MW | 250 | 52 | 302 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008961_001 | Dismissed | Planned | Production unavailability | 2024-03-27T11:39:35+00:00 | 2024-04-10T12:00:00+01:00 | 2024-04-26T12:00:00+01:00 | MW | 146 | 156 | 302 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_034 | Dismissed | Planned | Production unavailability | 2024-04-19T13:07:03+01:00 | 2023-07-18T14:00:00+01:00 | 2024-11-11T10:00:00+00:00 | MW | 0 | 0 | 0 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_033 | Dismissed | Planned | Production unavailability | 2024-04-19T13:04:31+01:00 | 2023-07-18T14:00:00+01:00 | 2024-11-11T10:00:00+00:00 | MW | 0 | 0 | 0 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_032 | Dismissed | Planned | Production unavailability | 2024-04-19T13:03:21+01:00 | 2023-07-18T14:00:00+01:00 | 2024-11-11T10:00:00+00:00 | MW | 0 | 138 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_031 | Dismissed | Planned | Production unavailability | 2024-04-19T13:02:21+01:00 | 2023-07-18T14:00:00+01:00 | 2024-11-11T10:00:00+00:00 | MW | 0 | 0 | 0 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_030 | Dismissed | Planned | Production unavailability | 2024-03-22T08:16:23+00:00 | 2023-07-18T14:00:00+01:00 | 2024-11-11T10:00:00+00:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_029 | Dismissed | Planned | Production unavailability | 2024-03-22T07:35:55+00:00 | 2023-07-18T14:00:00+01:00 | 2024-11-11T09:00:00+00:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_028 | Dismissed | Planned | Production unavailability | 2024-03-22T07:33:55+00:00 | 2023-07-18T14:00:00+01:00 | 2025-01-08T09:00:00+00:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_027 | Dismissed | Planned | Production unavailability | 2024-03-19T12:11:06+00:00 | 2023-07-18T14:00:00+01:00 | 2024-10-11T09:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_026 | Dismissed | Planned | Production unavailability | 2024-02-21T13:57:18+00:00 | 2023-07-18T14:00:00+01:00 | 2024-10-07T09:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_025 | Dismissed | Planned | Production unavailability | 2024-01-10T12:56:50+00:00 | 2023-07-18T14:00:00+01:00 | 2024-09-14T09:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_024 | Dismissed | Planned | Production unavailability | 2023-11-07T13:10:23+00:00 | 2023-07-18T14:00:00+01:00 | 2024-08-17T00:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_023 | Dismissed | Planned | Production unavailability | 2023-09-28T14:43:55+01:00 | 2023-07-18T14:00:00+01:00 | 2024-07-24T00:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_022 | Dismissed | Planned | Production unavailability | 2023-09-28T14:30:35+01:00 | 2023-07-18T14:00:00+01:00 | 2023-09-29T19:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_021 | Dismissed | Planned | Production unavailability | 2023-09-27T15:22:28+01:00 | 2023-07-18T14:00:00+01:00 | 2023-09-28T19:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_020 | Dismissed | Planned | Production unavailability | 2023-09-26T15:41:35+01:00 | 2023-07-18T14:00:00+01:00 | 2023-09-27T19:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_019 | Dismissed | Planned | Production unavailability | 2023-09-25T17:40:25+01:00 | 2023-07-18T14:00:00+01:00 | 2023-09-27T07:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_018 | Dismissed | Planned | Production unavailability | 2023-09-23T12:49:34+01:00 | 2023-07-18T14:00:00+01:00 | 2023-09-26T07:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_017 | Dismissed | Planned | Production unavailability | 2023-09-22T17:39:07+01:00 | 2023-07-18T14:00:00+01:00 | 2023-09-23T19:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_016 | Dismissed | Planned | Production unavailability | 2023-09-19T18:29:26+01:00 | 2023-07-18T14:00:00+01:00 | 2023-09-23T07:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_015 | Dismissed | Planned | Production unavailability | 2023-09-18T17:40:03+01:00 | 2023-07-18T14:00:00+01:00 | 2023-09-20T07:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_014 | Dismissed | Planned | Production unavailability | 2023-09-17T18:17:56+01:00 | 2023-07-18T14:00:00+01:00 | 2023-09-19T07:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_013 | Dismissed | Planned | Production unavailability | 2023-09-14T21:25:51+01:00 | 2023-07-18T14:00:00+01:00 | 2023-09-18T07:00:00+01:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |