Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 181 182 183 184 185 >
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007160_003 Dismissed Planned Production unavailability 2022-06-07T06:45:51+01:00 2022-06-07T10:00:00+01:00 2022-06-07T10:20:00+01:00 MW 893 0 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007160_002 Dismissed Planned Production unavailability 2022-06-06T20:05:50+01:00 2022-06-07T10:00:00+01:00 2022-06-07T10:30:00+01:00 MW 893 0 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007160_001 Dismissed Planned Production unavailability 2022-06-06T20:01:30+01:00 2022-06-07T10:00:00+01:00 2022-06-07T10:30:00+01:00 MW 0 893 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007159_003 Inactive Planned Production unavailability 2022-06-07T10:46:54+01:00 2022-06-07T09:30:00+01:00 2022-06-07T09:43:00+01:00 MW 766 127 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007159_002 Dismissed Planned Production unavailability 2022-06-07T09:40:34+01:00 2022-06-07T09:30:00+01:00 2022-06-07T09:43:00+01:00 MW 766 127 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007159_001 Dismissed Planned Production unavailability 2022-06-06T19:55:18+01:00 2022-06-07T09:30:00+01:00 2022-06-07T10:00:00+01:00 MW 766 127 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007162_007 Dismissed Planned Production unavailability 2022-06-07T10:24:40+01:00 2022-06-07T10:31:00+01:00 2022-06-07T11:30:00+01:00 MW 423 470 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007162_006 Dismissed Planned Production unavailability 2022-06-07T10:11:47+01:00 2022-06-07T10:31:00+01:00 2022-06-07T11:30:00+01:00 MW 423 470 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007162_005 Dismissed Planned Production unavailability 2022-06-07T09:49:04+01:00 2022-06-07T10:11:00+01:00 2022-06-07T11:30:00+01:00 MW 423 470 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007162_004 Dismissed Planned Production unavailability 2022-06-07T09:43:28+01:00 2022-06-07T10:04:00+01:00 2022-06-07T11:30:00+01:00 MW 423 470 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007162_003 Dismissed Planned Production unavailability 2022-06-07T08:32:53+01:00 2022-06-07T10:20:00+01:00 2022-06-07T11:30:00+01:00 MW 423 470 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007162_002 Dismissed Planned Production unavailability 2022-06-07T07:10:22+01:00 2022-06-07T11:00:00+01:00 2022-06-07T11:30:00+01:00 MW 423 470 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007162_001 Dismissed Planned Production unavailability 2022-06-06T20:18:51+01:00 2022-06-07T11:00:00+01:00 2022-06-07T12:00:00+01:00 MW 393 500 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007173_002 Dismissed Planned Production unavailability 2022-06-07T10:24:18+01:00 2022-06-07T13:00:00+01:00 2022-06-07T13:30:00+01:00 MW 121 772 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007173_001 Dismissed Planned Production unavailability 2022-06-07T07:25:25+01:00 2022-06-07T13:00:00+01:00 2022-06-07T13:30:00+01:00 MW 121 772 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007172_002 Dismissed Planned Production unavailability 2022-06-07T10:24:03+01:00 2022-06-07T12:30:00+01:00 2022-06-07T13:00:00+01:00 MW 200 693 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007172_001 Dismissed Planned Production unavailability 2022-06-07T07:20:07+01:00 2022-06-07T12:30:00+01:00 2022-06-07T13:00:00+01:00 MW 200 693 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007171_002 Dismissed Planned Production unavailability 2022-06-07T10:23:52+01:00 2022-06-07T12:00:00+01:00 2022-06-07T12:30:00+01:00 MW 273 620 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007171_001 Dismissed Planned Production unavailability 2022-06-07T07:17:17+01:00 2022-06-07T12:00:00+01:00 2022-06-07T12:30:00+01:00 MW 273 620 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007163_003 Dismissed Planned Production unavailability 2022-06-07T10:23:34+01:00 2022-06-07T11:30:00+01:00 2022-06-07T12:00:00+01:00 MW 353 540 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007163_002 Dismissed Planned Production unavailability 2022-06-07T07:15:34+01:00 2022-06-07T11:30:00+01:00 2022-06-07T12:00:00+01:00 MW 353 540 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007163_001 Dismissed Planned Production unavailability 2022-06-06T20:22:16+01:00 2022-06-07T12:00:00+01:00 2022-06-07T13:00:00+01:00 MW 203 690 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007170_002 Dismissed Planned Production unavailability 2022-06-07T10:23:04+01:00 2022-06-07T18:00:00+01:00 2022-06-07T18:30:00+01:00 MW 563 330 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007170_001 Dismissed Planned Production unavailability 2022-06-07T07:00:55+01:00 2022-06-07T18:00:00+01:00 2022-06-07T18:30:00+01:00 MW 563 330 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007166_002 Dismissed Planned Production unavailability 2022-06-07T10:22:50+01:00 2022-06-07T18:30:00+01:00 2022-06-08T08:00:00+01:00 MW 306 587 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007166_001 Dismissed Planned Production unavailability 2022-06-06T20:47:34+01:00 2022-06-07T18:30:00+01:00 2022-06-08T08:00:00+01:00 MW 306 587 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007169_002 Dismissed Planned Production unavailability 2022-06-07T10:22:22+01:00 2022-06-07T17:30:00+01:00 2022-06-07T18:00:00+01:00 MW 533 360 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007169_001 Dismissed Planned Production unavailability 2022-06-07T06:59:41+01:00 2022-06-07T17:30:00+01:00 2022-06-07T18:00:00+01:00 MW 533 360 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007168_002 Dismissed Planned Production unavailability 2022-06-07T10:22:04+01:00 2022-06-07T17:00:00+01:00 2022-06-07T17:30:00+01:00 MW 423 470 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007168_001 Dismissed Planned Production unavailability 2022-06-07T06:58:18+01:00 2022-06-07T17:00:00+01:00 2022-06-07T17:30:00+01:00 MW 423 470 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007158_002 Dismissed Planned Production unavailability 2022-06-07T10:21:33+01:00 2022-06-07T09:00:00+01:00 2022-06-07T09:30:00+01:00 MW 336 557 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007158_001 Dismissed Planned Production unavailability 2022-06-06T19:48:22+01:00 2022-06-07T09:00:00+01:00 2022-06-07T09:30:00+01:00 MW 336 557 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007165_003 Dismissed Planned Production unavailability 2022-06-07T10:21:01+01:00 2022-06-07T16:30:00+01:00 2022-06-07T17:00:00+01:00 MW 353 540 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007165_002 Dismissed Planned Production unavailability 2022-06-07T06:54:13+01:00 2022-06-07T16:30:00+01:00 2022-06-07T17:00:00+01:00 MW 353 540 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007165_001 Dismissed Planned Production unavailability 2022-06-06T20:37:20+01:00 2022-06-07T16:30:00+01:00 2022-06-07T18:30:00+01:00 MW 393 500 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007167_002 Dismissed Planned Production unavailability 2022-06-07T10:20:49+01:00 2022-06-07T16:00:00+01:00 2022-06-07T16:30:00+01:00 MW 273 620 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007167_001 Dismissed Planned Production unavailability 2022-06-07T06:53:36+01:00 2022-06-07T16:00:00+01:00 2022-06-07T16:30:00+01:00 MW 273 620 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007164_003 Dismissed Planned Production unavailability 2022-06-07T10:20:34+01:00 2022-06-07T15:30:00+01:00 2022-06-07T16:00:00+01:00 MW 203 690 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007164_002 Dismissed Planned Production unavailability 2022-06-07T06:48:54+01:00 2022-06-07T15:30:00+01:00 2022-06-07T16:00:00+01:00 MW 203 690 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007164_001 Dismissed Planned Production unavailability 2022-06-06T20:31:57+01:00 2022-06-07T15:30:00+01:00 2022-06-07T16:30:00+01:00 MW 203 690 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007155_004 Inactive Planned Production unavailability 2022-06-07T09:01:54+01:00 2022-06-06T18:36:00+01:00 2022-06-07T08:00:00+01:00 MW 273 620 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007155_003 Dismissed Planned Production unavailability 2022-06-06T19:40:44+01:00 2022-06-06T18:36:00+01:00 2022-06-07T08:00:00+01:00 MW 273 620 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007155_002 Dismissed Planned Production unavailability 2022-06-06T18:07:29+01:00 2022-06-06T18:36:00+01:00 2022-06-07T07:00:00+01:00 MW 273 620 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007155_001 Dismissed Planned Production unavailability 2022-06-05T17:27:30+01:00 2022-06-06T18:00:00+01:00 2022-06-07T07:00:00+01:00 MW 273 620 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007161_003 Dismissed Planned Production unavailability 2022-06-07T08:31:16+01:00 2022-06-07T10:20:00+01:00 2022-06-07T11:00:00+01:00 MW 623 270 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007161_002 Dismissed Planned Production unavailability 2022-06-07T06:46:39+01:00 2022-06-07T10:20:00+01:00 2022-06-07T11:00:00+01:00 MW 623 270 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007161_001 Dismissed Planned Production unavailability 2022-06-06T20:10:17+01:00 2022-06-07T10:30:00+01:00 2022-06-07T11:00:00+01:00 MW 621 272 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007141_002 Inactive Planned Production unavailability 2022-06-07T08:01:53+01:00 2022-06-06T19:00:00+01:00 2022-06-07T07:00:00+01:00 MW 273 620 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007141_001 Dismissed Planned Production unavailability 2022-06-01T12:59:17+01:00 2022-06-06T19:00:00+01:00 2022-06-07T07:00:00+01:00 MW 273 620 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000007156_003 Inactive Planned Production unavailability 2022-06-06T13:01:53+01:00 2022-06-06T11:30:00+01:00 2022-06-06T12:01:00+01:00 MW 150 0 150 Foreseen Maintenance
Plant Fault - Auxiliary Equipment
Hydro Pumped Storage 10YGB----------A