Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 142 143 144 145 146 > | ||||||||||||||||||
T_BEATO-1 | 48W00000BEATO-1T | SSE_GROUP |
48X0000000000319 | 0000000000000000000007648_002 | Inactive | Planned | Production unavailability | 2022-10-23T01:02:32+01:00 | 2022-10-20T00:00:00+01:00 | 2022-10-23T00:00:00+01:00 | MW | 2 | 124 | 126 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_BEATO-1 | 48W00000BEATO-1T | SSE_GROUP |
48X0000000000319 | 0000000000000000000007648_001 | Dismissed | Planned | Production unavailability | 2022-10-13T16:05:43+01:00 | 2022-10-20T00:00:00+01:00 | 2022-10-23T00:00:00+01:00 | MW | 2 | 124 | 126 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
CGT | 47W000000000443F | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000007647_001 | Dismissed | Planned | Production unavailability | 2022-10-13T16:04:50+01:00 | 2022-10-20T00:00:00+01:00 | 2022-10-23T00:00:00+01:00 | MW | 2 | 62 | 64 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007660_008 | Inactive | Unplanned | Production unavailability | 2022-10-21T19:02:32+01:00 | 2022-10-20T17:55:00+01:00 | 2022-10-21T18:00:00+01:00 | MW | 430 | 750 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007660_007 | Dismissed | Unplanned | Production unavailability | 2022-10-21T17:50:52+01:00 | 2022-10-20T17:55:00+01:00 | 2022-10-21T18:00:00+01:00 | MW | 430 | 750 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007660_006 | Dismissed | Unplanned | Production unavailability | 2022-10-21T13:03:11+01:00 | 2022-10-20T17:55:00+01:00 | 2022-10-22T20:00:00+01:00 | MW | 430 | 750 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007660_005 | Dismissed | Unplanned | Production unavailability | 2022-10-21T12:39:51+01:00 | 2022-10-20T17:55:00+01:00 | 2022-10-21T20:00:00+01:00 | MW | 430 | 750 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007660_004 | Dismissed | Unplanned | Production unavailability | 2022-10-20T21:02:19+01:00 | 2022-10-20T17:55:00+01:00 | 2022-10-21T14:30:00+01:00 | MW | 430 | 750 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007660_003 | Dismissed | Unplanned | Production unavailability | 2022-10-20T19:38:54+01:00 | 2022-10-20T17:55:00+01:00 | 2022-10-21T01:00:00+01:00 | MW | 430 | 750 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007660_002 | Dismissed | Unplanned | Production unavailability | 2022-10-20T19:14:13+01:00 | 2022-10-20T17:55:00+01:00 | 2022-10-20T20:30:00+01:00 | MW | 820 | 360 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007660_001 | Dismissed | Unplanned | Production unavailability | 2022-10-20T18:31:58+01:00 | 2022-10-20T17:55:00+01:00 | 2022-10-20T19:30:00+01:00 | MW | 200 | 980 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
TB3 | 47W0000000000994 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007620_006 | Inactive | Unplanned | Production unavailability | 2022-10-17T11:02:33+01:00 | 2022-09-22T15:27:00+01:00 | 2022-10-17T10:00:00+01:00 | MW | 241 | 0 | 241 | Failure | Plant Fault - Boiler |
Fossil Oil | 10Y1001A1001A59C |
TB3 | 47W0000000000994 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007620_005 | Dismissed | Unplanned | Production unavailability | 2022-10-14T11:20:52+01:00 | 2022-09-22T15:27:00+01:00 | 2022-10-17T10:00:00+01:00 | MW | 241 | 0 | 241 | Failure | Plant Fault - Boiler |
Fossil Oil | 10Y1001A1001A59C |
TB3 | 47W0000000000994 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007620_004 | Dismissed | Unplanned | Production unavailability | 2022-09-23T16:18:17+01:00 | 2022-09-22T15:27:00+01:00 | 2022-10-15T17:00:00+01:00 | MW | 241 | 0 | 241 | Failure | Plant Fault - Boiler |
Fossil Oil | 10Y1001A1001A59C |
TB3 | 47W0000000000994 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007620_003 | Dismissed | Unplanned | Production unavailability | 2022-09-23T09:43:18+01:00 | 2022-09-22T15:27:00+01:00 | 2022-09-27T18:00:00+01:00 | MW | 241 | 0 | 241 | Failure | Plant Fault - Boiler |
Fossil Oil | 10Y1001A1001A59C |
TB3 | 47W0000000000994 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007620_002 | Dismissed | Unplanned | Production unavailability | 2022-09-22T19:08:36+01:00 | 2022-09-22T15:27:00+01:00 | 2022-09-27T18:00:00+01:00 | MW | 241 | 0 | 241 | Failure | Plant Fault - Boiler |
Fossil Oil | 10Y1001A1001A59C |
TB3 | 47W0000000000994 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007620_001 | Dismissed | Unplanned | Production unavailability | 2022-09-22T16:10:11+01:00 | 2022-09-22T15:27:00+01:00 | 2022-09-23T18:00:00+01:00 | MW | 241 | 0 | 241 | Failure | Plant Fault - Boiler |
Fossil Oil | 10Y1001A1001A59C |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007650_003 | Inactive | Planned | Consumption unavailability | 2022-10-16T18:47:33+01:00 | 2022-10-16T12:00:00+01:00 | 2022-10-16T17:35:00+01:00 | MW | 0 | 150 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000007651_003 | Inactive | Planned | Consumption unavailability | 2022-10-16T18:47:33+01:00 | 2022-10-16T12:00:00+01:00 | 2022-10-16T17:35:00+01:00 | MW | 0 | 150 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007650_002 | Dismissed | Planned | Consumption unavailability | 2022-10-16T17:32:13+01:00 | 2022-10-16T12:00:00+01:00 | 2022-10-16T17:35:00+01:00 | MW | 0 | 150 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000007651_002 | Dismissed | Planned | Consumption unavailability | 2022-10-16T17:31:46+01:00 | 2022-10-16T12:00:00+01:00 | 2022-10-16T17:35:00+01:00 | MW | 0 | 150 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000007651_001 | Dismissed | Planned | Consumption unavailability | 2022-10-16T11:16:38+01:00 | 2022-10-16T12:00:00+01:00 | 2022-10-16T20:30:00+01:00 | MW | 0 | 150 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007650_001 | Dismissed | Planned | Consumption unavailability | 2022-10-16T11:14:23+01:00 | 2022-10-16T12:00:00+01:00 | 2022-10-16T20:30:00+01:00 | MW | 0 | 150 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000007613_002 | Inactive | Planned | Production unavailability | 2022-10-15T13:02:35+01:00 | 2022-10-14T06:00:00+01:00 | 2022-10-15T12:00:00+01:00 | MW | 0 | 80 | 80 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000007613_001 | Dismissed | Planned | Production unavailability | 2022-09-20T14:35:12+01:00 | 2022-10-14T06:00:00+01:00 | 2022-10-15T12:00:00+01:00 | MW | 0 | 80 | 80 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
Cloosh | 47W0000000003918 | CLOOSH VALLEY WIND FARM DESIGNATED ACTIVITY COMPANY |
47X0000000002099 | 0000000000000000000007649_003 | Inactive | Unplanned | Production unavailability | 2022-10-15T12:47:35+01:00 | 2022-10-15T09:47:00+01:00 | 2022-10-15T11:47:00+01:00 | MW | 105 | 0 | 105 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
Cloosh | 47W0000000003918 | CLOOSH VALLEY WIND FARM DESIGNATED ACTIVITY COMPANY |
47X0000000002099 | 0000000000000000000007649_002 | Dismissed | Unplanned | Production unavailability | 2022-10-15T10:42:25+01:00 | 2022-10-15T09:47:00+01:00 | 2022-10-15T11:47:00+01:00 | MW | 105 | 0 | 105 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
Cloosh | 47W0000000003918 | CLOOSH VALLEY WIND FARM DESIGNATED ACTIVITY COMPANY |
47X0000000002099 | 0000000000000000000007649_001 | Dismissed | Unplanned | Production unavailability | 2022-10-15T10:32:45+01:00 | 2022-10-15T09:47:00+01:00 | 2022-10-15T11:47:00+01:00 | MW | 0 | 105 | 105 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007643_004 | Inactive | Unplanned | Production unavailability | 2022-10-13T04:02:34+01:00 | 2022-10-11T22:10:00+01:00 | 2022-10-13T03:00:00+01:00 | MW | 400 | 780 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007643_003 | Dismissed | Unplanned | Production unavailability | 2022-10-13T02:14:47+01:00 | 2022-10-11T22:10:00+01:00 | 2022-10-13T03:00:00+01:00 | MW | 400 | 780 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007643_002 | Dismissed | Unplanned | Production unavailability | 2022-10-12T08:56:35+01:00 | 2022-10-11T22:10:00+01:00 | 2022-10-14T08:00:00+01:00 | MW | 400 | 780 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007643_001 | Dismissed | Unplanned | Production unavailability | 2022-10-11T22:14:03+01:00 | 2022-10-11T22:10:00+01:00 | 2022-10-13T20:00:00+01:00 | MW | 400 | 780 | 1180 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007645_002 | Inactive | Unplanned | Production unavailability | 2022-10-12T16:02:33+01:00 | 2022-10-12T09:45:00+01:00 | 2022-10-12T15:00:00+01:00 | MW | 624 | 131 | 755 | Failure | Plant Fault - Electrical Equipment |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007645_001 | Dismissed | Unplanned | Production unavailability | 2022-10-12T09:46:00+01:00 | 2022-10-12T09:45:00+01:00 | 2022-10-12T15:00:00+01:00 | MW | 624 | 131 | 755 | Failure | Plant Fault - Electrical Equipment |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007646_004 | Inactive | Unplanned | Production unavailability | 2022-10-12T14:40:37+01:00 | 2022-10-12T12:22:00+01:00 | 2022-10-12T13:15:00+01:00 | MW | 820 | 360 | 1180 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007646_003 | Dismissed | Unplanned | Production unavailability | 2022-10-12T13:13:56+01:00 | 2022-10-12T12:22:00+01:00 | 2022-10-12T13:15:00+01:00 | MW | 820 | 360 | 1180 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007646_002 | Dismissed | Unplanned | Production unavailability | 2022-10-12T12:50:45+01:00 | 2022-10-12T12:22:00+01:00 | 2022-10-12T13:55:00+01:00 | MW | 820 | 360 | 1180 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007646_001 | Dismissed | Unplanned | Production unavailability | 2022-10-12T12:24:00+01:00 | 2022-10-12T12:22:00+01:00 | 2022-10-12T13:00:00+01:00 | MW | 940 | 240 | 1180 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007644_004 | Inactive | Unplanned | Production unavailability | 2022-10-12T10:32:34+01:00 | 2022-10-12T08:26:00+01:00 | 2022-10-12T09:30:00+01:00 | MW | 755 | 0 | 755 | Failure | Plant Fault - Auxiliary Equipment |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007644_003 | Dismissed | Unplanned | Production unavailability | 2022-10-12T09:13:09+01:00 | 2022-10-12T08:26:00+01:00 | 2022-10-12T09:30:00+01:00 | MW | 755 | 0 | 755 | Failure | Plant Fault - Auxiliary Equipment |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007644_002 | Dismissed | Unplanned | Production unavailability | 2022-10-12T09:09:58+01:00 | 2022-10-12T08:26:00+01:00 | 2022-10-12T09:10:00+01:00 | MW | 755 | 0 | 755 | Failure | Plant Fault - Auxiliary Equipment |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007644_001 | Dismissed | Unplanned | Production unavailability | 2022-10-12T08:26:42+01:00 | 2022-10-12T08:26:00+01:00 | 2022-10-12T09:00:00+01:00 | MW | 755 | 0 | 755 | Failure | Plant Fault - Auxiliary Equipment |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007635_002 | Inactive | Planned | Production unavailability | 2022-10-12T01:02:33+01:00 | 2022-10-06T13:00:00+01:00 | 2022-10-11T23:59:00+01:00 | MW | 755 | 0 | 755 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007635_001 | Dismissed | Planned | Production unavailability | 2022-10-06T12:38:43+01:00 | 2022-10-06T13:00:00+01:00 | 2022-10-11T23:59:00+01:00 | MW | 755 | 0 | 755 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
RHODE1 | 47W000000000212Y | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007642_004 | Inactive | Unplanned | Production unavailability | 2022-10-10T17:01:54+01:00 | 2022-10-07T17:00:00+01:00 | 2022-10-10T16:00:00+01:00 | MW | 52 | 0 | 52 | Failure | Plant Fault - Electrical Equipment |
Fossil Gas | 10Y1001A1001A59C |
RHODE1 | 47W000000000212Y | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007642_003 | Dismissed | Unplanned | Production unavailability | 2022-10-10T12:53:34+01:00 | 2022-10-07T17:00:00+01:00 | 2022-10-10T16:00:00+01:00 | MW | 52 | 0 | 52 | Failure | Plant Fault - Electrical Equipment |
Fossil Gas | 10Y1001A1001A59C |
RHODE1 | 47W000000000212Y | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007642_002 | Dismissed | Unplanned | Production unavailability | 2022-10-08T16:06:16+01:00 | 2022-10-07T17:00:00+01:00 | 2022-10-10T13:00:00+01:00 | MW | 52 | 0 | 52 | Failure | Plant Fault - Electrical Equipment |
Fossil Gas | 10Y1001A1001A59C |
RHODE1 | 47W000000000212Y | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007642_001 | Dismissed | Unplanned | Production unavailability | 2022-10-07T18:31:44+01:00 | 2022-10-07T17:00:00+01:00 | 2022-10-08T17:00:00+01:00 | MW | 52 | 0 | 52 | Failure | Plant Fault - Electrical Equipment |
Fossil Gas | 10Y1001A1001A59C |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007636_005 | Inactive | Planned | Consumption unavailability | 2022-10-07T23:02:34+01:00 | 2022-10-07T00:45:00+01:00 | 2022-10-07T22:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Weather |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000007637_005 | Inactive | Planned | Consumption unavailability | 2022-10-07T23:02:34+01:00 | 2022-10-07T00:45:00+01:00 | 2022-10-07T22:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Weather |
Hydro Pumped Storage | 10YGB----------A |